SEARCH YOUR QUERY

Monday, July 5, 2021

Q bank on Schedule of Dimensions for Civil Engineering LDC Exam - MCQ (New Pattern)

(1) The minimum centre to centre distance of a B.G. track in mid-section is ........... mm 
(a)4200
(b)4265
(C) 4350 
(d) 4000
Answer - (b)4265

(2) Any deviations from the Schedule of dimensions will require prior sanction of .......... 
(a) Zonal Rly 
(b) Rly Board 
(c) CRS
(d) All of them 
Answer -(b) Rly Board 

(3) The maximum gradient in station yards should be ....... Unless special safely devices are adopted and/or special rules enforced. 
(a) 1 in 400
(B) 1 in 500 
(c) 1 in 1000 
(D) 1 In 600
Answer -(a) 1 in 400

(4) The recommended maximum gradient in the year for B.G is- 
 (a) 1 in 1000 
 (b) 1 in 1200
 ( c) 1 in 1500 
 (d) 1 in 1800
Answer - (b) 1 in 1200


 (5)For B.G. the minimum radius of a curve is ......... 
 (a) 150m 
 (b) 175
 (c) 200m
(d) 225m
Answer - (b) 175

(6) Check rails should normally be provided where the radius is ....... M or less in B.G. 
 (a) 150m 
 (b) 200m 
 (c) 208m* 
 (d) 225m
Answer - (c) 208m* 

(7) On B.G. maximum clearances of check rails at a level crossing are 
 (a) 51mm 
 ( b ) 57mm* 
 (c) 65mm 
 (d) 54mm 
Answer - ( b ) 57mm* 

 (8) Minimum depth of space for wheel flange form rail level in B.G. is ...... mm 
 (A) 35 
 (B) 38* 
 (C) 42 
 (D) 45 
Answer - (B) 38* 

 ( 9 ) The minimum horizontal distances form centre of track to face of passenger platform coping for B.G. is ....... Mm 
(A)1650 MM. 
(B)1670 MM* 
(C)1676 MM 
(D) 1685 MM 
Answer -(B)1670 MM* 

(10) What is maximum height above rail level for low-level passenger platform for BG? 
(a) 300mm 
(b) 455mm* 
(c) 525mm 
(d) 550mm
Answer -(b) 455mm* 

(11) Maximum curvature permitted on B.G. is 
(a) 8 degree 
(b) 10 degree* 
(c) 12 degree 
(d) 16 degree
Answer -(b) 10 degree* 

(12) The minimum track centres in B.G. double line is
(a)4500 mm 
(b)4750 mm 
(c) 5000 mm 
(d) 5300 mm
Answer -(d) 5300 mm

(13) Maximum height of rolling stock on BG should be
(a) 2745mm 
(b) 3250mm 
(c) 3450mm 
(d) 4140mm
Answer -(d) 4140mm

(14) Maximum width of rolling stock on BG should be 
(a)4745mm
(b)3250mm
(c) 3450mm 
(d) 4140mm
Answer -(b)3250mm

(15) The gradient of a platform is generally 
(a) 1 in 1000 
(b) 1 in 750 
(c) 1 in 500
(d) 1 in 250 
Answer -(c) 1 in 500

(16) Maximum clearance of check rails at level crossing for B.G. should be
(a)48mm 
(b)57mm
(c)51mm
(d)44mm
Answer -(b)57mm

(17) Height gauges should be located at a minimum distance of..... from gate post. 
 (a) 5 m 
 (b) 7.5m 
 (c) 8m* 
 (d)10m 
Answer - (c) 8m* 

 (18) O.D.C. Stands for 
 (a) On direct current 
 (b) Over dimensioned consignment* 
 (c) None of them 
 (d) Operating & gate
Answer - (b) Over dimensioned consignment* 

(19) In case of ‘A’ Class ODC escort is........... 
 (a) Necessary 
 (b) not necessary
 (c) does not matter 
 (d) on direct current 
Answer - (b) not necessary

(20) For A class ODC, the gross clearance over maximum moving dimension of B.G is
(a)150mm 
(b) 175mm
(c)225 mm
(d) 250mm 
Answer -(c)225 mm

(21) For A Class, the gross clearance of over maximum moving dimension for BG is 
(a)100mm 
(b)125mm
(c) 150mm
(d) 175mm
Answer -(c) 150mm

(22) Check rails should normally be provided where the radius is .... M or less in B.G. 
 (a) 150m 
 (b) 200m 
 (c) 218m* 
 (d) 240m
Answer - (c) 218m

(23) On B.G. maximum clearances of check rails at a level crossing are 
(a) 51 mm 
(b) 57mm*
(c) 65mm 
(d) 70mm 
Answer -(b) 57mm

(24) The maximum height above rail level for B.G. goods platform is ....... Mm
(a)1000mm
(b)1050mm
(c)1065mm*
(d)1075mm 
Answer - (c)1065mm

(25) Minimum clearance of check rails for B.G. at level crossing should be
(a) 48mm 
(b) 57mm 
(c) 51mm
(d) 44mm
Answer - (c) 51mm

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.

Index -

01. INTEGRATED CONCEPT AND OBJECTIVES OF MATERIALS MANAGEMENT (1) 01.02 रेलपथ निरक्षक तथा सहायक मंडल अभियंता के कर्तव्य (1) 02 रेलपथ (1) 02. ORGANIZATION OF MATERIALS MANAGEMENT DEPARTMENT (1) 02.01 90 यूटीएस रेलों के सम्भाल (1) 02.04 रेल तापमान (1) 02.05 रेल जोड (1) 03 स्लीपरो के कार्य (1) 03. CLASSIFICATION/CODIFICATION NOMENCLATURE OF STORES ON INDIAN RAILWAYS (1) 03.01 विभिन्न प्रकार के स्लीपरो की तुलना (1) 03.02 लचीले बंधन (1) 03.03 स्लीपर बिछाना (1) 04. PLANNING OF NON-STOCK ITEMS AND PROCESSING OF REQUISITION (1) 04.01 ट्रैक के लिए बैलास्ट प्रोफाइल (1) 04.02 फार्मेशन (1) 04.03 ब्रिज (पुल) (1) 05 पाइंट्स तथा क्रासिंग - परिचय एवं परिभाषाए (1) 05 PLANNING OF STOCK ITEMS & SYSTEMS OF RECOUPMENT (1) 05.01 विषेश ले आउट (1) 05.02 पृथक्रकरण (आइसोलेशन ) (1) 05.03 तथा क्रासिंग का अनुरक्षण तथा निरक्षण (1) 05.04 पॉइंट्स एवं क्रासिंग की (1) 06 गोलाई का प्ररंभिक ज्ञान (1) 06 PURCHASE POLICY (1) 06.01 वर्को का पुनः संरेखण (1) 07 Purchase Procedure on zonal Railways (1) 08 TENDER EVALUATION AND MISCELLANEOUS POLICY ISSUES IN PURCHASES (1) 08.01 व्यव्स्तिथ ओवरहालिंग (1) 08.02 रेलपथ अनुरक्षण का वार्षिक कार्यक्रम (1) 08.04 गहरी छनाई (1) 08.04.1 रेलपथ का उठाना लोवेरिंग तथा क्रीप (1) 08.05 छोटी वेल्डेड रेल ( एसडब्लूआर ) (1) 08.06 आन ट्रैक मशीन (1) 08.07 छोटी ट्रैक मशीने (1) 08.09 विद्युतीकृत सेक्शन में हाइट गेज (1) 08.11 अंडर ट्रायल सामग्री का रिकॉर्ड (1) 09 गति प्रतिबन्ध और संकेतक (1) 09 Receipt And Inspection of stores (1) 09.01 ठेकेदार की सुरक्षित कार्य प्रणाली (1) 09.03 रेल संरक्षा आयुक्त की स्वीकृति वाले कार्य (1) 10 निरक्षण का उद्देश्य (1) 10 ISSUE AND DISTRIBUTION OF STORES (1) 10.01 राइडिंग गुणवत्ता तथा राइडिंग इंडेक्स (1) 10.03 सिटीआर तथा टीजीआई (1) 10.04 रेलपथ प्रबंधन पध्दति (टीऍमएस ) (1) 11 RETURNED STORES (1) 11.01 स्लीपरो का बिछाना (1) 12 दुर्घटना (1) 12 Scrap Disposal (1) 12.01 ब्रीच (1) 12.02 डाईवर्शन (1) 13 INVENTORY MANAGEMENT (1) 14 लंबी वेल्डित रेल (परिभाषाए) (1) 14.01 एलडब्लूआर / सीडब्लूआरके लिये स्वीकृत स्थान (1) 14.02 एलडब्लूआरकी डीस्ट्रेसिंग (1) 14.03 एलडब्लूआर / सीडब्लूआर का अनुरक्षण (1) 14.04 रेलपथ पर्येवेक्षक - मेट तथा चाबीदार के लिए अनुमत तथा निषिद्ध कार्य (1) 15 - सर्वेक्षण (1) 15 बयाना राशि और जमानत राशि (1) 15.01 SURVEYING (2) 16 रेलवे टेंडर सिस्टम (Railway Tender System) (1) Accidents (2) Active & Passive Earth Pressure (1) Anti corrosive treatment (1) Ballast (2) Bearings in Bridge (1) Blanketing Material (1) Bridges (2) Buckling of track (1) Building Work (1) Cant deficiency & Cant Excess (1) Census (1) Chequered Tiles (1) Chlorination of Water (2) Chlorination Practices (1) Chlorine demand (1) Civil Engineering - Bridges (2) Civil Engineering - P Way (40) Civil Engineering - Works (5) CMS Crossing (1) Completion report (1) Contour & Contour interval (1) Correction Slip (1) CRS Sanction (1) CTR and TGI Value (1) Curing of Concrete (1) curves (2) Deep Screening (2) Design mode (1) Design of concrete mix (2) Destressing (1) Disinfection of water (1) disposal of human waste: (1) Distressed bridges (2) Distressing of LWR (2) distribution System (1) dry density (1) Duties (3) Duties & Responsibilities (9) Duties of Gateman (1) E01.02 Duties of Keyman / Mate / PWS (1) E02.01 Permanent Way (1) E02.02 Handling of 90 UTS rails (1) E02.05 Rail Temperature (1) E02.06 Rail Joints (1) E02.07 Maintenance of Rail Joints (1) E03.01 SLEEPERS AND FASTENINGS - Functions of Sleepers (1) E03.02 Comparison between Various Types of Sleepers (1) E03.04 Laying of Sleepers (1) E04.02 Ballast Profile for L.W.R. track (1) E04.04 Bridges (1) E05.01 Points & Crossings: Introduction & Definitions (1) E05.04 Maintenance and Inspection of Points and Crossing (1) E05.05 Reconditioning of Points and Crossing (1) E06.01 Basics of Curves (1) E06.02 Realignment of Curve (1) E08.01 MAINTENANCE OF TRACK-Through packing (1) E08.02 Systematic Overhauling (1) E08.03 Annual Programme for Regular Track Maintenances (1) E08.04 Lifting/ Lowering of Track and Creep (1) E08.05 Deep Screening (1) E08.06 Short Welded Rail (1) E08.07 Maintenance of SWR (1) E08.10 Level Crossing (1) E08.11 Equipments at Level Crossing (1) E08.12 Maintenance / Examination / Inspection of Level Crossing / Gate (1) E08.14 Welding of Rails (1) E08.15 Records of Material under Trial (As per Cs.no 99) (1) E09.01 Speed Restriction and Indicators (1) E09.02 Safe Working of Contractors (As per Cs.No 95) (1) E09.03 Works Requiring CRS Sanction (1) E10.01 INSPECTION OF TRACK - Object of Inspection (1) E10.02 Riding Quality and Riding Index (1) E10.03 Track Recording and Oscillograph Car (1) E10.04 CTR and TGI Value (1) E12.01 ACCIDENTS AND BREACHES - Accidents (1) E12.02 Breaches (1) E12.03 Diversion (1) E14.01 LONG WELDED RAIL - Definitions (1) E14.02 Permitted locations for LWR/CWR (1) E14.04 Maintenance of LWR / CWR (1) E14.05 DOs and Don’ts OF LWR For PWM / MATES & KEYMAN (1) Egineering (1) Elastic Fastening (1) Elastic Rail Clip (1) Encroachments of Railway land. (2) Engineering (26) Engineering - Book (3) Examination of Rails (2) Fabrication of Glued joint IN SITU. (1) Flushing cisterns (1) FOB (1) Gateman (2) Greasing of ERCs (1) Grow More Food Scheme (1) Guideline (3) H02 भण्डार विभाग का महत्व (1) H03 भण्डार डिपो की संरचना (1) H04 भण्डार का वर्गीकरण (1) H05 कोडिफीकेशन (1) H06 मानकीकरण एवं उसकी उपयोगिता (1) H07 वित्तीय औचित्य के सिध्दांत (1) H08 क्रय के विभिन्न माध्यम (1) H09 क्रय में विविध अधिमान्यताए (1) H10 भण्डार विभाग के अधिकारियो की क्रय शक्तियां (1) H12 निविदा समिति (1) H13 अनुबंध (1) H16 स्थानीय खरीद (1) H17 भण्डार डिपो में भण्डार प्राप्ति के स्त्रोत (1) H18 महत्वपूर्ण वस्तुए एवं उनकी खरीद (1) H19 भण्डार डिपो का संगठन एवं कार्य (1) H20 प्राप्ति अनुभाग की क्रिया - विधि (1) H21 वार्ड की क्रिया - विधि (1) H22 प्रेषण अनुभाग की क्रिया - विधि (1) H23 बहीखाता अनुभाग की क्रिया - विधि (1) H24 डिपो प्रणाली (1) H25 भण्डार का निरीक्षण (1) H26 अस्वीकृत भण्डार (1) H27 लौटाया गया भण्डार (1) H28 अग्रदाय भण्डार (1) H29 अधिशेष भण्डार (1) H30 रेल सामग्री की बिक्री (1) H31 रद्दी माल और नीलामी बिक्रिया (1) H32 वस्तु - सूची नियंत्रण (1) H33 स्टॉक सत्यापन (1) H34 मांगकरताओ व्दारा डिपुओ से भण्डार प्राप्त करने की प्रक्रिया (1) H35 संक्षिप्त टिप्पणीयां (1) Handling of 90 UTS Rails (1) Height Gauges on Electrified Section (1) Honey combing of concrete & its prevention (1) Hot Weather Patrolling (1) Imprest Store (1) INDEX (2) Indicator Boards & Signages (1) Inspection (6) Insulated joints (1) Isolation (1) Keyman / Mate / PWS (3) Laying of Sleepers (1) LDCE Exam (3) Level Crossing (2) Level crossings (2) Licensing Railway Land cultivation (1) Liner Biting (1) LWR (6) Maintenance (2) Maintenance in Electrified Area (2) Maintenance of CMS Xing (1) Maintenance of P Way (5) Maintenance of Rail Joints (1) Maintenancee of SWR (1) Manson precaution (1) Monsoon Patrolling (2) Numerical rating system (NRS) (1) Optimum moisture content (1) P Way (23) Pandrol Clip (1) pass (1) Patrolling of Rail Permanent Way (6) Permanent Way (2) Permanent Way (P Way) (10) Pile Foundation (1) Points and Crossing (3) Protection of Rail (1) Pumping Water Level (1) PWI (1) PWI / AEN / DEN (1) quality control (2) Question & Answer (62) Rail Clusters (1) Rail Formation (2) rail fracture (1) Rail Joints (1) Rail Renewal (3) Rail Welding (3) Rails Defects (2) Railway Affecting Works (1) Railway Construction (1) Railway Organisation (2) Realignments of Curve) (1) Reconditioning of Points and Crossing (1) Rehabilitation of Bridges (1) Renewal of Rail (1) River Training protection work (1) safe speed (1) Safe Working (1) Safety at P. Way Work Site (1) Schedule of Inspection of Bridges (1) Short Note - Bridge (8) Short Note - P Way (48) Short Note - Works (35) Short Notes - Mislanious (7) Sleeper (4) Sleeper Cribs (1) Soil Consistency (1) Special Layouts (2) Speed Restriction and Indicators (2) Static Water Level (1) Steel Structures (1) Stock sheet (1) Store (34) super elevation (1) Tender System (1) Testing of Rails (2) TGI and OMS (1) Thermit Welding (1) Through Parking (2) Tiles (2) Track Circuited Areas (2) Track Inspection (1) Track Machines (6) Track Management System (1) Track Tolerances (2) track-Overhauling (1) Transitions (1) Turnout (1) urinals (1) USFD (2) Venerable location (1) VIDEO (2) wash basin. (1) Washable Aprons (1) Water Cement ratio (1) Water closetsu (1) Water Quality (1) Water Supply (1) Waterproofing (1) weld failure (1) Well Foundation (1) Winter Precautions (1) Workability of Concrete (1) Working of Contractors (2) works (9) कार्य एवं उद्देश्य (1) ट्रैक रिकॉर्डिंग तथा दोलन लेखी कार (1) रेल पथ मेट के कर्तव्य (1)