SEARCH YOUR QUERY

Monday, July 12, 2021

Q Bank on BRIDGE for Civil Engineer LDC Exam MCQ New Pattern

Q 1 What do you understand by Camber, Dead load camber and Live load camber in steel triangulated (Open web) girders? What do you mean by Loss of camber and the reasons for it?

Answer: - camber: - It is the curvature/ deflection intentionally induced in the Girder to compensate for deflection which is to be encountered by it, during service for a particular designed load.The part of the camber corresponding to dead load is called dead load camber and the balance left over is called Live load camber, which should be available as visible and measurable camber in the girder when not carrying load.

Loss of camber: - It is the loss in deflection between the initially induced deflection and that measured at any interval of time with no live load.

The loss of camber is due to:- Over stressing of members beyond the elastic limit.Over stressing of Joint Rivets. Loose Rivets.

Q 2. Give planning of construction of subway (LHS) in place of level Xing including block working within 5.30 hours and what precautions to be taken during block working and in monsoon.

Ans  Criteria:- The level crossing having following condition should be identified to replace with LHS.

I.Accident prone LC’s where visibility is not clear 

II.Where embankment height is at least 3 met. 

 III.Where TVU is less but have potential of getting manned level crossing 

IV.Other condition as required. 

Methodology of execution:- there are various methods such as 

I.Pre cast box segment placing (Cut & Cover method )

II.Placement of Precast box after inserting RH girder 

III.Box pushing IV.Box puling

V.Cast in Situ The most popular method is cut & cover as per planning boxes to be casted in cess and then If 5:30 hrs block is required to do the work

I.Track dismantling & ballast removal - 25 minuet

II.Earth work in cutting - 60 minuet

III.Sand filling in Bed- 15 minuet

IV.Slab Placing- 30 minuet

V.Box placing - 100 minuet

VI.Geo Textile and Geo membrane- 30 minuet

VII.Back filling- 20 minuet

VIII.Ballast putting- 20 minuet

IX.Track linking - 30 minuet 


Equipment required at site during block:- 

I.Crawler crane cap-125 ton.- 02 Nos. + 01 No for emergency

II.Poclain- 02 Nos. +01 No. For emergency

III.JCB- 02 Nos.

IV.Tippers - 02 Nos. 

V.Water Tanker- 01 Nos. 

VI.Gas Cutting and welding set- 01 Nos. 

VII.Men Power- 60 Nos. 

Cut and cover method include following steps :- 

I.Demarcation at site:- Demarcation at site is a pre block activity so that should be done as per site requirement well before block started .

II.Track dismantling and removal of ballast :- these activities should be done as per demarcation at the site with the help of adequate men and machine power. Dismantled material should be placed out of working space and within a easy approach to facilitate at the time of restoration work. 

III.Earth cutting :- Earth cutting will be done with the help of poclain and JCB. And slop in cutting is maintained in the ratio of 2:1 to 1:2:1 depending upon the local condition of earth.

IV.Send filling :- send filling with 150 mm in thickness is done over a levelled and compacted surface

V.Slab Placing :- precast slabs are placed over levelled bed of send with the help of crane and the joints of slab are filled with appropriate material. 

VI.Box Placing:- the precast RCC boxes are placed as per fresh demarcation over precast slab with the help of crane in proper alignment.

VII.Geo Textile and Geo membrane :- Geo Textile is provided to the surface exposed to earth and ballast to cover the tope and side of boxes in order to filter the water during rain and the Geo membrane is pasted at the joints of boxes with the help of flame to check the flow (seapage) of water through joints of boxes.

VIII.Back filling :- Back filleting is done with machine to fill the space between side of box and embankment across the track and get compacted simultaneously.

IX.Ballast Putting:- Ballast putting is done with the help of men and machine available at site as per track profile .

X.Track linking:- Track linking is done over spreaded ballast and then track is linked with the existing track with all relevant activities and traffic to allow with S.R.Precautions:- 

1.Earth cutting to be done properly with proper slope and care should taken that it should not falled and labours/supervisor should be keep safe distance.

2.Sand begs should be provided to bank to retain earth. 

3.Sling should check4.After linking track should packed and XL and gauge should check. 

Q.3 Explain classification of railway bridges. Define distressed bridge and its category and frequency of inspection. Write the various steps for inspection of triangulated girder through bridge.

1)Important bridges: Important bridges is one which has a very large size of waterway. As per the old practice*, the bridge having total areas of water-way of 110 sq. metre (1200 sq. ft.) and more, or having linear water-way of 180 metres (600 ft) or more, was classified as an ‘Important Bridge’ . The criteria for classifying the bridge has recently been revised by the Railway board.** as per the revised standers ,a bridge is an ‘Important bridge’ if it has total area of water –way of more than 1000 sq. metres or has linear water-way more than 300 metres.

2)Major bridge: major bridge is one, which have a total linear water 0 way of 18 metres (60 ft) or more or which have a clear opening of 12 metres (40 ft) or more.

3)Minor Bridge: The bridge having linear water-way of less than 12 metres (40 ft) in case of single span bridge and less than 18 meters (60 ft) in case of multipal span bridge is called a ‘minor bridge’

4)Culvert: a very small bridge is called a ‘culvert’. Normally a bridge, having span of less than 6 meters, may be called a culvert.

DISTRESSED BRIDGES

1.Definition of distressed bridge 

A  distressed bridge is one which shows some physical deterioration of its physical condition, indicating the need for rehabilitation through special repairs, strengthening or rebuilding (including replacement of girders).

2.Classification of distressed bridge

Category-1: Those requiring rehabilitation to be done immediately, say with in a year’s time.

Category-2: Those requiring to be kept under observation and to be taken up for rehabilitation on a programme basis.

Group 1: Distressed bridges in Group 1 category are recommended for speed restriction upto 15 KMPH.

Group 2: Distressed bridges in Group 2 category are recommended for speed restriction 25 KMPH to 40 KMPH. 

Schedule of inspection of distressed bridges.


Category                             Inspection By                                     Periodicity

1.(a)                         Inspector (concerned)                             Once in a month
(b)                                AEN or ABE                                     Once in two months
(c)                            DEN or Sr. DEN                                   Once in three months

2.                          (a)Inspector (concerned)                          Once in three months

(b)                        AEN or ABE                                             Once in a six months
(c)                       DEN or Sr. DEN                                           Once in a yea

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.

Index -

01. INTEGRATED CONCEPT AND OBJECTIVES OF MATERIALS MANAGEMENT (1) 01.02 रेलपथ निरक्षक तथा सहायक मंडल अभियंता के कर्तव्य (1) 02 रेलपथ (1) 02. ORGANIZATION OF MATERIALS MANAGEMENT DEPARTMENT (1) 02.01 90 यूटीएस रेलों के सम्भाल (1) 02.04 रेल तापमान (1) 02.05 रेल जोड (1) 03 स्लीपरो के कार्य (1) 03. CLASSIFICATION/CODIFICATION NOMENCLATURE OF STORES ON INDIAN RAILWAYS (1) 03.01 विभिन्न प्रकार के स्लीपरो की तुलना (1) 03.02 लचीले बंधन (1) 03.03 स्लीपर बिछाना (1) 04. PLANNING OF NON-STOCK ITEMS AND PROCESSING OF REQUISITION (1) 04.01 ट्रैक के लिए बैलास्ट प्रोफाइल (1) 04.02 फार्मेशन (1) 04.03 ब्रिज (पुल) (1) 05 पाइंट्स तथा क्रासिंग - परिचय एवं परिभाषाए (1) 05 PLANNING OF STOCK ITEMS & SYSTEMS OF RECOUPMENT (1) 05.01 विषेश ले आउट (1) 05.02 पृथक्रकरण (आइसोलेशन ) (1) 05.03 तथा क्रासिंग का अनुरक्षण तथा निरक्षण (1) 05.04 पॉइंट्स एवं क्रासिंग की (1) 06 गोलाई का प्ररंभिक ज्ञान (1) 06 PURCHASE POLICY (1) 06.01 वर्को का पुनः संरेखण (1) 07 Purchase Procedure on zonal Railways (1) 08 TENDER EVALUATION AND MISCELLANEOUS POLICY ISSUES IN PURCHASES (1) 08.01 व्यव्स्तिथ ओवरहालिंग (1) 08.02 रेलपथ अनुरक्षण का वार्षिक कार्यक्रम (1) 08.04 गहरी छनाई (1) 08.04.1 रेलपथ का उठाना लोवेरिंग तथा क्रीप (1) 08.05 छोटी वेल्डेड रेल ( एसडब्लूआर ) (1) 08.06 आन ट्रैक मशीन (1) 08.07 छोटी ट्रैक मशीने (1) 08.09 विद्युतीकृत सेक्शन में हाइट गेज (1) 08.11 अंडर ट्रायल सामग्री का रिकॉर्ड (1) 09 गति प्रतिबन्ध और संकेतक (1) 09 Receipt And Inspection of stores (1) 09.01 ठेकेदार की सुरक्षित कार्य प्रणाली (1) 09.03 रेल संरक्षा आयुक्त की स्वीकृति वाले कार्य (1) 10 निरक्षण का उद्देश्य (1) 10 ISSUE AND DISTRIBUTION OF STORES (1) 10.01 राइडिंग गुणवत्ता तथा राइडिंग इंडेक्स (1) 10.03 सिटीआर तथा टीजीआई (1) 10.04 रेलपथ प्रबंधन पध्दति (टीऍमएस ) (1) 11 RETURNED STORES (1) 11.01 स्लीपरो का बिछाना (1) 12 दुर्घटना (1) 12 Scrap Disposal (1) 12.01 ब्रीच (1) 12.02 डाईवर्शन (1) 13 INVENTORY MANAGEMENT (1) 14 लंबी वेल्डित रेल (परिभाषाए) (1) 14.01 एलडब्लूआर / सीडब्लूआरके लिये स्वीकृत स्थान (1) 14.02 एलडब्लूआरकी डीस्ट्रेसिंग (1) 14.03 एलडब्लूआर / सीडब्लूआर का अनुरक्षण (1) 14.04 रेलपथ पर्येवेक्षक - मेट तथा चाबीदार के लिए अनुमत तथा निषिद्ध कार्य (1) 15 - सर्वेक्षण (1) 15 बयाना राशि और जमानत राशि (1) 15.01 SURVEYING (2) 16 रेलवे टेंडर सिस्टम (Railway Tender System) (1) Accidents (2) Active & Passive Earth Pressure (1) Anti corrosive treatment (1) Ballast (2) Bearings in Bridge (1) Blanketing Material (1) Bridges (2) Buckling of track (1) Building Work (1) Cant deficiency & Cant Excess (1) Census (1) Chequered Tiles (1) Chlorination of Water (2) Chlorination Practices (1) Chlorine demand (1) Civil Engineering - Bridges (2) Civil Engineering - P Way (40) Civil Engineering - Works (5) CMS Crossing (1) Completion report (1) Contour & Contour interval (1) Correction Slip (1) CRS Sanction (1) CTR and TGI Value (1) Curing of Concrete (1) curves (2) Deep Screening (2) Design mode (1) Design of concrete mix (2) Destressing (1) Disinfection of water (1) disposal of human waste: (1) Distressed bridges (2) Distressing of LWR (2) distribution System (1) dry density (1) Duties (3) Duties & Responsibilities (9) Duties of Gateman (1) E01.02 Duties of Keyman / Mate / PWS (1) E02.01 Permanent Way (1) E02.02 Handling of 90 UTS rails (1) E02.05 Rail Temperature (1) E02.06 Rail Joints (1) E02.07 Maintenance of Rail Joints (1) E03.01 SLEEPERS AND FASTENINGS - Functions of Sleepers (1) E03.02 Comparison between Various Types of Sleepers (1) E03.04 Laying of Sleepers (1) E04.02 Ballast Profile for L.W.R. track (1) E04.04 Bridges (1) E05.01 Points & Crossings: Introduction & Definitions (1) E05.04 Maintenance and Inspection of Points and Crossing (1) E05.05 Reconditioning of Points and Crossing (1) E06.01 Basics of Curves (1) E06.02 Realignment of Curve (1) E08.01 MAINTENANCE OF TRACK-Through packing (1) E08.02 Systematic Overhauling (1) E08.03 Annual Programme for Regular Track Maintenances (1) E08.04 Lifting/ Lowering of Track and Creep (1) E08.05 Deep Screening (1) E08.06 Short Welded Rail (1) E08.07 Maintenance of SWR (1) E08.10 Level Crossing (1) E08.11 Equipments at Level Crossing (1) E08.12 Maintenance / Examination / Inspection of Level Crossing / Gate (1) E08.14 Welding of Rails (1) E08.15 Records of Material under Trial (As per Cs.no 99) (1) E09.01 Speed Restriction and Indicators (1) E09.02 Safe Working of Contractors (As per Cs.No 95) (1) E09.03 Works Requiring CRS Sanction (1) E10.01 INSPECTION OF TRACK - Object of Inspection (1) E10.02 Riding Quality and Riding Index (1) E10.03 Track Recording and Oscillograph Car (1) E10.04 CTR and TGI Value (1) E12.01 ACCIDENTS AND BREACHES - Accidents (1) E12.02 Breaches (1) E12.03 Diversion (1) E14.01 LONG WELDED RAIL - Definitions (1) E14.02 Permitted locations for LWR/CWR (1) E14.04 Maintenance of LWR / CWR (1) E14.05 DOs and Don’ts OF LWR For PWM / MATES & KEYMAN (1) Egineering (1) Elastic Fastening (1) Elastic Rail Clip (1) Encroachments of Railway land. (2) Engineering (26) Engineering - Book (3) Examination of Rails (2) Fabrication of Glued joint IN SITU. (1) Flushing cisterns (1) FOB (1) Gateman (2) Greasing of ERCs (1) Grow More Food Scheme (1) Guideline (3) H02 भण्डार विभाग का महत्व (1) H03 भण्डार डिपो की संरचना (1) H04 भण्डार का वर्गीकरण (1) H05 कोडिफीकेशन (1) H06 मानकीकरण एवं उसकी उपयोगिता (1) H07 वित्तीय औचित्य के सिध्दांत (1) H08 क्रय के विभिन्न माध्यम (1) H09 क्रय में विविध अधिमान्यताए (1) H10 भण्डार विभाग के अधिकारियो की क्रय शक्तियां (1) H12 निविदा समिति (1) H13 अनुबंध (1) H16 स्थानीय खरीद (1) H17 भण्डार डिपो में भण्डार प्राप्ति के स्त्रोत (1) H18 महत्वपूर्ण वस्तुए एवं उनकी खरीद (1) H19 भण्डार डिपो का संगठन एवं कार्य (1) H20 प्राप्ति अनुभाग की क्रिया - विधि (1) H21 वार्ड की क्रिया - विधि (1) H22 प्रेषण अनुभाग की क्रिया - विधि (1) H23 बहीखाता अनुभाग की क्रिया - विधि (1) H24 डिपो प्रणाली (1) H25 भण्डार का निरीक्षण (1) H26 अस्वीकृत भण्डार (1) H27 लौटाया गया भण्डार (1) H28 अग्रदाय भण्डार (1) H29 अधिशेष भण्डार (1) H30 रेल सामग्री की बिक्री (1) H31 रद्दी माल और नीलामी बिक्रिया (1) H32 वस्तु - सूची नियंत्रण (1) H33 स्टॉक सत्यापन (1) H34 मांगकरताओ व्दारा डिपुओ से भण्डार प्राप्त करने की प्रक्रिया (1) H35 संक्षिप्त टिप्पणीयां (1) Handling of 90 UTS Rails (1) Height Gauges on Electrified Section (1) Honey combing of concrete & its prevention (1) Hot Weather Patrolling (1) Imprest Store (1) INDEX (2) Indicator Boards & Signages (1) Inspection (6) Insulated joints (1) Isolation (1) Keyman / Mate / PWS (3) Laying of Sleepers (1) LDCE Exam (3) Level Crossing (2) Level crossings (2) Licensing Railway Land cultivation (1) Liner Biting (1) LWR (6) Maintenance (2) Maintenance in Electrified Area (2) Maintenance of CMS Xing (1) Maintenance of P Way (5) Maintenance of Rail Joints (1) Maintenancee of SWR (1) Manson precaution (1) Monsoon Patrolling (2) Numerical rating system (NRS) (1) Optimum moisture content (1) P Way (23) Pandrol Clip (1) pass (1) Patrolling of Rail Permanent Way (6) Permanent Way (2) Permanent Way (P Way) (10) Pile Foundation (1) Points and Crossing (3) Protection of Rail (1) Pumping Water Level (1) PWI (1) PWI / AEN / DEN (1) quality control (2) Question & Answer (62) Rail Clusters (1) Rail Formation (2) rail fracture (1) Rail Joints (1) Rail Renewal (3) Rail Welding (3) Rails Defects (2) Railway Affecting Works (1) Railway Construction (1) Railway Organisation (2) Realignments of Curve) (1) Reconditioning of Points and Crossing (1) Rehabilitation of Bridges (1) Renewal of Rail (1) River Training protection work (1) safe speed (1) Safe Working (1) Safety at P. Way Work Site (1) Schedule of Inspection of Bridges (1) Short Note - Bridge (8) Short Note - P Way (48) Short Note - Works (35) Short Notes - Mislanious (7) Sleeper (4) Sleeper Cribs (1) Soil Consistency (1) Special Layouts (2) Speed Restriction and Indicators (2) Static Water Level (1) Steel Structures (1) Stock sheet (1) Store (34) super elevation (1) Tender System (1) Testing of Rails (2) TGI and OMS (1) Thermit Welding (1) Through Parking (2) Tiles (2) Track Circuited Areas (2) Track Inspection (1) Track Machines (6) Track Management System (1) Track Tolerances (2) track-Overhauling (1) Transitions (1) Turnout (1) urinals (1) USFD (2) Venerable location (1) VIDEO (2) wash basin. (1) Washable Aprons (1) Water Cement ratio (1) Water closetsu (1) Water Quality (1) Water Supply (1) Waterproofing (1) weld failure (1) Well Foundation (1) Winter Precautions (1) Workability of Concrete (1) Working of Contractors (2) works (9) कार्य एवं उद्देश्य (1) ट्रैक रिकॉर्डिंग तथा दोलन लेखी कार (1) रेल पथ मेट के कर्तव्य (1)