Purchase Procedure on zonal Railways

7.0.0 Introduction to purchase procedure :

We are purchasing out of public exchequer and therefore we have to take precautions that public money is most efficiently used and we get best value of the Rupee. To meet this objective and also comply with purchase policies of Government of India, we have designed the purchase procedures in such a manner that we are able to meet these basic objectives and at the same time, are able to follow various policy guidelines of Government of India on purchase matters. The procedure should also ensure that purchase action is initiated against all the demands sent to purchase office and all avoidable delays in purchases are eliminated. Purchase procedures followed on most of the Railways is described in the following paragraphs.
7.1.0 Receipt and Registration of Demands :

All the requests for purchase of materials are known by the name 'Demand'. 
  • A demand may be either
  • A stock recoupment sheet or
  • Estimate sheet submitted by the Stores Depot for recouping a stock item or
  • It may be a requisition received directly from the user department which, mostly, is for a non-stock item (but in some exceptional cases, there may be direct requisition even for a stock item).
  • All these demands are received in COS's Office in a separate section known as 'Central Registration Section'. On some of the Railways, there may be separate sections to receive estimate sheets/recoupment sheets submitted by the depots because, they have to be compiled in one purchase case before initiating purchase.
  • On receipt in Central Registration Section, all the demands are scrutinized to see that they are duly signed by the competent authorities and required information such as Description, Quantity, Consignee Allocation, funds' certification are clearly indicated and also vetting of associate finance, wherever required has been obtained.
  • All these demands are then entered in a register which is maintained purchase section-wise. All the demands which, prima- facie, appear incomplete, are returned to the indentors for furnishing complete information and the remaining are forwarded to respective purchase sections.

7.1.1 The Demand Registration No. : It is given by central registration section is of eight digits.

 First two digits indicate code of purchase section in which the purchase will be dealt, 
 Next two digits indicate year of registration and
 Last four digits indicate serial number of registration under that purchase section. \

To distinguish direct demands from estimate sheets/recoupment sheet received from depots, all estimate sheets / recoupment sheets submitted by the depot for stock items are registered from Serial Number 0001 to 4999 and the demands registered for SL. No. 5000 onward are for the requisitions submitted by the indentors.

7.1.2 Allotment of Registration no: This demand registration no. is advised by the central registration section to respective stores depot or indentor, as the case may be, with the advice that this number should invariably be referred in all future correspondences.

7.2.0 Preparation of purchase proposal :

7.2.1 When the demand has been received in the purchase section, action to arrange the material is initiated. First of all, it is checked up whether the demand can be met with inactive / surplus / overstocks available on other Railways/production units. If so, a requisition or final purchase order is placed on the concerned Railway / Production unit. It may also be possible that demand of one depot may be met with overstock in other depot and in that case, a depot transfer order may be issued.

7.2.2 If the item is DGS & D or Railway Board item or it is to be arranged through some other centralized purchase agency, then an indent is sent to that agency. On some Railways, there is separate Indent section for preparation and follow up of indents.

7.2.3 If the item is available on DGS & D rate contract or rate contract finalized by any other centralized agency, which can be operated by COS, supply order is placed against the rate contract. If the parallel rate contracts exist in favor of many firms, the particular firm on whom the order is to be placed is selected on the basis of its performance and comparative rate.

7.2.4 If the material cannot be arranged by any of the above methods, then direct purchase is initiated. First of all, a purchase proposal is prepared which contains basic details of demand (requisition or estimate sheet). At this stage, it is also seen whether any other demand for the same item is pending for initiating purchase action. If so, that demand is also clubbed with correct case to get advantage of buying in bulk quantity. In a purchase proposal, details of last successful purchase are invariably furnished because estimated value of purchase is worked out on the basis of last purchase rate after taking other factors also into consideration.

7.2.5 This purchase proposal is then put up by the purchase section to the respective purchase officer, depending upon purchase powers and estimated value of purchase of that particular item. As per present delegation, COS is empowered to authorize and sanction purchases up to Rs.1 Crore, CMM up to Rs.50 lakhs, Dy. COS up to Rs.5 lakhs, Senior Stores Officer up to Rs.75,000 and an ACOS up to Rs.25,000. However , these delegations may vary from Railway to Railway.

7.3.0 Decision on Method of Purchase and Mode of Tendering :

7.3.1 When the case is put up to purchase officer, he has to decide about the method of purchase. Our normal method of purchase is through tender system and therefore, purchase officer will pass orders in the file for mode of tendering out of three modes of tender systems. If the orders are being passed for inviting limited tenders, then the purchase officer will also specify whether the item is to be included in weekly stores bulletin or separate tender inquiries are to be issued. If separate tender inquiries are suggested, then panel of firms to whom tender inquiries are to be sent is also to be approved. Similarly, in case of single tender, name of firm to whom single tender is to be issued is also to be approved.

7.4.0 Tender Invitation :

7.4.1 After obtaining orders from purchase officer, tender documents are prepared. If open tenders are to be issued, then a tender notice is prepared and sent to Chief Public Relations Officer for publication in the newspapers. Tender documents are then forwarded to the centralized tender section for sale to firms on payment. If the item is to be included in the Weekly Stores Bulletin, then information on the prescribed proforma ,is prepared and sent to bulletin section for further compilation. Ordinary or special limited tender inquiries are directly dispatched to suppliers by Registered AD or under postal certificate (UPC).

7.4.2 All the tenders, irrespective of their type, bear due date and time by which offers should be submitted.

7.4.3 After this, purchase case is transferred to tender section for further dealing.

7.5.0 Opening of Tenders :

7.5.1 On the due date and time, tenders are opened. There is an elaborate system for tender opening to ensure that all the tenders submitted by the firms are properly linked in the respective cases and any additions or alterations after opening of the tenders are not possible.

7.5.2 All advertised tenders and special limited tenders (tenders in which estimated value of purchase is more than Rs. 3 lakhs) are opened in public and firms' representatives who want to be present during opening are allowed to be present.

Such tenders, should be opened by a Gazetted Officer from Stores Department and at least a Section Officer from Accounts Department.

All limited tenders are opened by a Chief Clerk/Head Clerk from Stores Department and a Senior Clerk from Accounts Department. At the time of opening of these tenders, firm's representatives are
not allowed to be present.

7.5.3 After opening these are signed by the tender opening officials on each page and all financial aspects are encircled, overwriting etc. are also attested. Then the tenders are sorted tender case-wise (please note that at this stage, Demand No. is generally referred as Tender No. on some Railways)

7.5.4 After sorting, tenders are linked in the respective tender cases and then they are transferred to respective purchase officers. However, in all the cases in which lowest tender is valuing more than Rs.2 lakhs, detailed abstract of all tenders (also known as tabulation statement) is prepared and also got vetted from Accounts department.

7.5.5 After this, the tender case is passed on to respective purchase officer on the basis of value of lowest tender.

7.6.0 Decision of Tenders :

7.6.1 The tenders are now to be decided to either accept the suitable offer out of all the tenders received or reject or file them. All the tenders in which acceptable offer is less than or equal to Rs. 3 lakhs can be decided by the respective purchase officer as per the purchase powers delegated to him but, if the acceptable offer is valuing more than Rs. 3 lakhs, then the tenders have to be discussed by a tender committee consisting of 3 officers, one from Stores Department one from consuming department and one from Accounts Department. From Stores and consuming department, officers below the rank of senior scale cannot be the members of a tender committee and Accounts member is generally one grade lower e.g., tenders valuing from Rs. 3 to 8 lakhs are discussed by senior scale officers from Stores and consuming department and an Asst./Junior scale officer from Accounts Department. Tender Committee is always a recommending body and its recommendations have to be accepted by a competent accepting officer.

7.6.2 Some of the points to be kept in mind for deciding tenders are as under:

(a) The offer should be technically suitable i.e. the material offered by the firm should be exactly as per our specifications given in the tender inquiry. Offers of substandard materials are normally ignored;

(b) Out of all technically suitable offers, lowest offer is examined for reasonableness of rates.

(c) If the rate of lowest technically suitable offer is considered reasonable, then it is to be seen whether delivery offered by the firm will meet our requirement with respect to delivery period and

place of delivery.

(d) After satisfying about (a), (b) & (c) above, we see that the firm is reliable and has satisfactory record of past performance.

(e) Finally before accepting the offer, we see that all terms and conditions offered by the firm are acceptable. We normally, place all our purchase orders as per 'Indian Railways Standard (IRS) Conditions of Contracts.' As per these conditions, we have right to reject the substandard materials, levy liquidated damages for delayed supplies, make risk purchases, etc.

7.7.0 Placement of Purchase Order :

7.7.1 When the tenders have been decided, purchase officer records acceptance on the tender accepted by him and then the purchase case is passed on to the respective purchase section for preparation of purchase order.

7.7.2 After the purchase order has been signed by the purchase officer, it is sent to Accounts Department for pre-check if the value is more than Rs.40,000/-. 7.7.3 All purchase orders issued against demands submitted by Stores Depots for stock items, availability of funds out of purchase grant is to be ascertained from Accounts Department. For this purpose, Accounts Department is maintaining an up-to-date liability register. At the time of issue of purchase order, value of purchase order is posted in liability register and a funds certificate is recorded on the purchase order.

7.7.4 Finally, the purchase order is numbered. Purchase Order Number. consists of 16 digits out of which first 8 digits are same as Demand No. or Tender No., 9th digit indicates mode of purchase, 10 th to 14th digits are serial number which are allotted paying authority-wise, 15th & 16th digit indicates serial No. of the item, consignee, delivery date if there are more than one item, consignee, delivery dates respectively in the purchase order.

7.7.5 After numbering, the purchase order is dispatched to suppliers by registered post with Acknowledge Due.

7.8.0 Contract Administration :

7.8.1 The purchase activity is not over only on placement of purchase order. For getting the material in time, contract has to be properly administered. Immediately on placement of orders or after some time, we may get request from supplier for amending some of the clauses of the purchase order. All these requests have to be examined in proper perspective and amendments (or modification advises) against the purchase orders are issued. For all the amendments which may result into financial repercussions, we may have to take finance concurrence.

7.8.2 If the supplier is not able to supply the materials within the stipulated delivery period, then as per law of contract, contract expires. Further extension has to be with mutual consent. Normally suppliers request for extension of delivery date and this is examined keeping all relevant factors in mind. As per IRS conditions of contract, we have right to recover liquidated damages for any loss or inconvenience suffered by us due to delays in supply of material.

7.8.3 Sometimes, firms fail to supply the materials. As per IRS conditions of contract, if the firm fails to supply the material, we can purchase the material from the alternative sources at the risk and cost of the supplier i.e. if we pay any higher prices to the alternative source, the difference can be recovered from the defaulter. These purchases from alternative sources are known as Risk Purchase. In order to ensure that risk purchase is legally tenable, we have to follow certain procedures by which
reasonable opportunity to make good the loss is given to the supplier and the risk purchase has to be arranged within a reasonable time (which is normally 6 months) from the date of breach of contract.

7.8.4 Arbitration : Sometimes disputes may arise in the execution of the contracts. If the dispute can not be mutually settled, then as per IRS conditions of contract, it is to be referred to a sole arbitrator appointed by the General Manager and decision of the arbitrator will be final in such a case.

7.9.0 Supply of materials :

Materials against purchase orders placed by Controller of Stores are supplied to the consignees mentioned in the purchase order. Material received can be pre-inspected by inspecting agencies like RITES, RDSO, DOI or can be got inspected on receipt. Decision for acceptance or rejection of the material is conveyed to the supplier, COS Office, Bill passing agency etc., through issue of vouchers like Receipt Notes, passing of bills, Rejection advice etc.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.

Index -

01. INTEGRATED CONCEPT AND OBJECTIVES OF MATERIALS MANAGEMENT (1) 01.02 रेलपथ निरक्षक तथा सहायक मंडल अभियंता के कर्तव्य (1) 02 रेलपथ (1) 02. ORGANIZATION OF MATERIALS MANAGEMENT DEPARTMENT (1) 02.01 90 यूटीएस रेलों के सम्भाल (1) 02.04 रेल तापमान (1) 02.05 रेल जोड (1) 03 स्लीपरो के कार्य (1) 03. CLASSIFICATION/CODIFICATION NOMENCLATURE OF STORES ON INDIAN RAILWAYS (1) 03.01 विभिन्न प्रकार के स्लीपरो की तुलना (1) 03.02 लचीले बंधन (1) 03.03 स्लीपर बिछाना (1) 04. PLANNING OF NON-STOCK ITEMS AND PROCESSING OF REQUISITION (1) 04.01 ट्रैक के लिए बैलास्ट प्रोफाइल (1) 04.02 फार्मेशन (1) 04.03 ब्रिज (पुल) (1) 05 पाइंट्स तथा क्रासिंग - परिचय एवं परिभाषाए (1) 05 PLANNING OF STOCK ITEMS & SYSTEMS OF RECOUPMENT (1) 05.01 विषेश ले आउट (1) 05.02 पृथक्रकरण (आइसोलेशन ) (1) 05.03 तथा क्रासिंग का अनुरक्षण तथा निरक्षण (1) 05.04 पॉइंट्स एवं क्रासिंग की (1) 06 गोलाई का प्ररंभिक ज्ञान (1) 06 PURCHASE POLICY (1) 06.01 वर्को का पुनः संरेखण (1) 07 Purchase Procedure on zonal Railways (1) 08 TENDER EVALUATION AND MISCELLANEOUS POLICY ISSUES IN PURCHASES (1) 08.01 व्यव्स्तिथ ओवरहालिंग (1) 08.02 रेलपथ अनुरक्षण का वार्षिक कार्यक्रम (1) 08.04 गहरी छनाई (1) 08.04.1 रेलपथ का उठाना लोवेरिंग तथा क्रीप (1) 08.05 छोटी वेल्डेड रेल ( एसडब्लूआर ) (1) 08.06 आन ट्रैक मशीन (1) 08.07 छोटी ट्रैक मशीने (1) 08.09 विद्युतीकृत सेक्शन में हाइट गेज (1) 08.11 अंडर ट्रायल सामग्री का रिकॉर्ड (1) 09 गति प्रतिबन्ध और संकेतक (1) 09 Receipt And Inspection of stores (1) 09.01 ठेकेदार की सुरक्षित कार्य प्रणाली (1) 09.03 रेल संरक्षा आयुक्त की स्वीकृति वाले कार्य (1) 10 निरक्षण का उद्देश्य (1) 10 ISSUE AND DISTRIBUTION OF STORES (1) 10.01 राइडिंग गुणवत्ता तथा राइडिंग इंडेक्स (1) 10.03 सिटीआर तथा टीजीआई (1) 10.04 रेलपथ प्रबंधन पध्दति (टीऍमएस ) (1) 11 RETURNED STORES (1) 11.01 स्लीपरो का बिछाना (1) 12 दुर्घटना (1) 12 Scrap Disposal (1) 12.01 ब्रीच (1) 12.02 डाईवर्शन (1) 13 INVENTORY MANAGEMENT (1) 14 लंबी वेल्डित रेल (परिभाषाए) (1) 14.01 एलडब्लूआर / सीडब्लूआरके लिये स्वीकृत स्थान (1) 14.02 एलडब्लूआरकी डीस्ट्रेसिंग (1) 14.03 एलडब्लूआर / सीडब्लूआर का अनुरक्षण (1) 14.04 रेलपथ पर्येवेक्षक - मेट तथा चाबीदार के लिए अनुमत तथा निषिद्ध कार्य (1) 15 - सर्वेक्षण (1) 15 बयाना राशि और जमानत राशि (1) 15.01 SURVEYING (2) 16 रेलवे टेंडर सिस्टम (Railway Tender System) (1) Accidents (2) Active & Passive Earth Pressure (1) Anti corrosive treatment (1) Ballast (2) Bearings in Bridge (1) Blanketing Material (1) Bridges (2) Buckling of track (1) Building Work (1) Cant deficiency & Cant Excess (1) Census (1) Chequered Tiles (1) Chlorination of Water (2) Chlorination Practices (1) Chlorine demand (1) Civil Engineering - Bridges (2) Civil Engineering - P Way (41) Civil Engineering - Works (5) CMS Crossing (1) Completion report (1) Contour & Contour interval (1) Correction Slip (1) CRS Sanction (1) CTR and TGI Value (1) Curing of Concrete (1) curves (2) Deep Screening (2) Design mode (1) Design of concrete mix (2) Destressing (1) Disinfection of water (1) disposal of human waste: (1) Distressed bridges (2) Distressing of LWR (2) distribution System (1) dry density (1) Duties (3) Duties & Responsibilities (9) Duties of Gateman (1) E01.02 Duties of Keyman / Mate / PWS (1) E02.01 Permanent Way (1) E02.02 Handling of 90 UTS rails (1) E02.05 Rail Temperature (1) E02.06 Rail Joints (1) E02.07 Maintenance of Rail Joints (1) E03.01 SLEEPERS AND FASTENINGS - Functions of Sleepers (1) E03.02 Comparison between Various Types of Sleepers (1) E03.04 Laying of Sleepers (1) E04.02 Ballast Profile for L.W.R. track (1) E04.04 Bridges (1) E05.01 Points & Crossings: Introduction & Definitions (1) E05.04 Maintenance and Inspection of Points and Crossing (1) E05.05 Reconditioning of Points and Crossing (1) E06.01 Basics of Curves (1) E06.02 Realignment of Curve (1) E08.01 MAINTENANCE OF TRACK-Through packing (1) E08.02 Systematic Overhauling (1) E08.03 Annual Programme for Regular Track Maintenances (1) E08.04 Lifting/ Lowering of Track and Creep (1) E08.05 Deep Screening (1) E08.06 Short Welded Rail (1) E08.07 Maintenance of SWR (1) E08.10 Level Crossing (1) E08.11 Equipments at Level Crossing (1) E08.12 Maintenance / Examination / Inspection of Level Crossing / Gate (1) E08.14 Welding of Rails (1) E08.15 Records of Material under Trial (As per Cs.no 99) (1) E09.01 Speed Restriction and Indicators (1) E09.02 Safe Working of Contractors (As per Cs.No 95) (1) E09.03 Works Requiring CRS Sanction (1) E10.01 INSPECTION OF TRACK - Object of Inspection (1) E10.02 Riding Quality and Riding Index (1) E10.03 Track Recording and Oscillograph Car (1) E10.04 CTR and TGI Value (1) E12.01 ACCIDENTS AND BREACHES - Accidents (1) E12.02 Breaches (1) E12.03 Diversion (1) E14.01 LONG WELDED RAIL - Definitions (1) E14.02 Permitted locations for LWR/CWR (1) E14.04 Maintenance of LWR / CWR (1) E14.05 DOs and Don’ts OF LWR For PWM / MATES & KEYMAN (1) Egineering (1) Elastic Fastening (1) Elastic Rail Clip (1) Encroachments of Railway land. (2) Engineering (26) Engineering - Book (3) Examination of Rails (2) Fabrication of Glued joint IN SITU. (1) Flushing cisterns (1) FOB (1) Gateman (2) Greasing of ERCs (1) Grow More Food Scheme (1) Guideline (3) H02 भण्डार विभाग का महत्व (1) H03 भण्डार डिपो की संरचना (1) H04 भण्डार का वर्गीकरण (1) H05 कोडिफीकेशन (1) H06 मानकीकरण एवं उसकी उपयोगिता (1) H07 वित्तीय औचित्य के सिध्दांत (1) H08 क्रय के विभिन्न माध्यम (1) H09 क्रय में विविध अधिमान्यताए (1) H10 भण्डार विभाग के अधिकारियो की क्रय शक्तियां (1) H12 निविदा समिति (1) H13 अनुबंध (1) H16 स्थानीय खरीद (1) H17 भण्डार डिपो में भण्डार प्राप्ति के स्त्रोत (1) H18 महत्वपूर्ण वस्तुए एवं उनकी खरीद (1) H19 भण्डार डिपो का संगठन एवं कार्य (1) H20 प्राप्ति अनुभाग की क्रिया - विधि (1) H21 वार्ड की क्रिया - विधि (1) H22 प्रेषण अनुभाग की क्रिया - विधि (1) H23 बहीखाता अनुभाग की क्रिया - विधि (1) H24 डिपो प्रणाली (1) H25 भण्डार का निरीक्षण (1) H26 अस्वीकृत भण्डार (1) H27 लौटाया गया भण्डार (1) H28 अग्रदाय भण्डार (1) H29 अधिशेष भण्डार (1) H30 रेल सामग्री की बिक्री (1) H31 रद्दी माल और नीलामी बिक्रिया (1) H32 वस्तु - सूची नियंत्रण (1) H33 स्टॉक सत्यापन (1) H34 मांगकरताओ व्दारा डिपुओ से भण्डार प्राप्त करने की प्रक्रिया (1) H35 संक्षिप्त टिप्पणीयां (1) Handling of 90 UTS Rails (1) Height Gauges on Electrified Section (1) Honey combing of concrete & its prevention (1) Hot Weather Patrolling (1) Imprest Store (1) INDEX (2) Indicator Boards & Signages (1) Inspection (6) Insulated joints (1) Isolation (1) Keyman / Mate / PWS (3) Laying of Sleepers (1) LDCE Exam (3) Level Crossing (2) Level crossings (2) Licensing Railway Land cultivation (1) Liner Biting (1) LWR (6) Maintenance (2) Maintenance in Electrified Area (2) Maintenance of CMS Xing (1) Maintenance of P Way (5) Maintenance of Rail Joints (1) Maintenancee of SWR (1) Manson precaution (1) Monsoon Patrolling (2) Numerical rating system (NRS) (1) Optimum moisture content (1) P Way (23) Pandrol Clip (1) pass (1) Patrolling of Rail Permanent Way (6) Permanent Way (2) Permanent Way (P Way) (10) Pile Foundation (1) Points and Crossing (3) Protection of Rail (1) Pumping Water Level (1) PWI (1) PWI / AEN / DEN (1) quality control (2) Question & Answer (62) Rail Clusters (1) Rail Formation (2) rail fracture (1) Rail Joints (1) Rail Renewal (3) Rail Welding (3) Rails Defects (2) Railway Affecting Works (1) Railway Construction (1) Railway Organisation (2) Realignments of Curve) (1) Reconditioning of Points and Crossing (1) Rehabilitation of Bridges (1) Renewal of Rail (1) River Training protection work (1) safe speed (1) Safe Working (1) Safety at P. Way Work Site (1) Schedule of Inspection of Bridges (1) Short Note - Bridge (8) Short Note - P Way (48) Short Note - Works (35) Short Notes - Mislanious (7) Sleeper (4) Sleeper Cribs (1) Soil Consistency (1) Special Layouts (2) Speed Restriction and Indicators (2) Static Water Level (1) Steel Structures (1) Stock sheet (1) Store (34) super elevation (1) Tender System (1) Testing of Rails (2) TGI and OMS (1) Thermit Welding (1) Through Parking (2) Tiles (2) Track Circuited Areas (2) Track Inspection (1) Track Machines (6) Track Management System (1) Track Tolerances (2) track-Overhauling (1) Transitions (1) Turnout (1) urinals (1) USFD (2) Venerable location (1) VIDEO (2) wash basin. (1) Washable Aprons (1) Water Cement ratio (1) Water closetsu (1) Water Quality (1) Water Supply (1) Waterproofing (1) weld failure (1) Well Foundation (1) Winter Precautions (1) Workability of Concrete (1) Working of Contractors (2) works (9) कार्य एवं उद्देश्य (1) ट्रैक रिकॉर्डिंग तथा दोलन लेखी कार (1) रेल पथ मेट के कर्तव्य (1)