Correction Slip No.18 to the Indian Railways Permanent Way Manual 2020





INDIAN RAILWAYS PERMANENT WAY MANUAL, 2020 ADDENDUM AND CORRIGENDUM SLIP NO.18 DATED 15.03.2024


1.0 The existing Table-III{Para 637(2) }under heading "Deep Screening with BCM (Ballast Cleaning Machine)" of IRPWM, 2020 shall be replaced by new Table-III{Para 637(2)) of IRPWM, 2020 as under:


Table- III


SCHEDULE OF SPEED RESTRICTION FOR DEEP SCREENING BY BCM FOLLOWED BY TAMPING AND STABILIZATION BY DYNAMIC TRACK STABILIZER (DTS) MACHINE


Details of work


Days of work


Speed Restriction


40 Kmph


Deep screening of track by BCM, ballast equalization followed by initial packing and initial stabilization by DTS in maximum settlement mode.


1st day


First round of tamping followed by stabilization of track by DTS in maximum settlement mode.


2nd day (1st Tamping)


40 Kmph


Ballasting for recoupment of ballast deficiency (if required), boxing of ballast section and tidying.


3rd day


40 Kmph


Boxing of ballast section and tidying.


4th day


40 Kmph


40 Kmph


Second round of tamping followed by stabilization of track by DTS in maximum settlement mode.


5th day (2nd Tamping)


Survey of track for design mode tamping as per annexure 2.16 of IRTMM, boxing of ballast section and tidying.


6th day


75 Kmph


Inspection of track, boxing of ballast section and tidying.


Third round of tamping in design mode followed by two rounds of stabilization of track by DTS in controlled settlement mode.


7th day


75 Kmph


8th day (3rd tamping)


110 Kmph


Footplate/last vehicle inspection and speed raising.


10th day


130 Kmph


Footplate/last vehicle inspection and speed raising


12th day


160 Kmph


Note: The period of schedule shown above can be suitably increased to suit local conditions of track consolidation. Full ballasting as per prescribed ballast profile to be ensured before the third round of tamping


2.0 Para 708 may be modified as under:


708 Speed Restrictions The speed restrictions to be imposed during various sequences of work are given in Table I, II and III which are as shown below:


Table-I-No Change


Table-II(A), II(B) and II(C)- No Change


A new Table-III(A) "Mechanized laying of track by Track Laying Equipment (TLE) followed by machine tamping without Dynamic Track Stablizer (DTS)" & new Table III(B) "Mechanized


laying of track by Track Relaying Train (TRT) followed by machine tamping without DTS"


are added as under:-


15-3.24

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.