SEARCH YOUR QUERY

Monday, April 8, 2024

Examination of Rails

Rails should be inspected for flaws specially, when the rails show signs of fatigue and the rail wear is excessive. The detection of rail flaws is done either by visual examination of the rail or by ultrasonic rail flaw detection.

1.Visual examination of Rails –

Most of the rail flaws develop at the rail ends. Rail ends should be examined for cracks during the lubrication of rail joints by cleaning the surface of the rail by wire brushes and using a magnifying glass. A small mirror is of assistance in examining the underside of rails. Such an inspection on the important girder bridges and their approaches should be done twice a year.

2.Ultrasonic testing of rails–

Ultrasonic testing of rails is specialized activity and the inspectors carrying out the ultrasonic testing of rails shall be trained by RDSO, in the technique of USFD  testing. Each zonal railway shall create adequate number of excadre posts of inspectors to ensure that entire track length in their jurisdiction is ultrasonically tested at the laid down periodicity. 

Rail testing by ultrasonic method shall be carried out by RDSO approved single rail testing trolley or double testing trolley and rig for 450 probes. Details of frequency and number of each type of probes are as under:

(As per USFD Manual Cs.no 2)

Water is used as couplant while testing with Single Rail Testers/Double Rail Testers.

This is supplied through a water container attached with the trolley. Soft grease to RDSO Specification No. WD-17-MISC. - 92 is to be used as couplant while deploying 45º probes with test rig”.

(As per USFD Manual Cs.no 3)

"Any sweeping signal on horizontal baseline that does not extend beyond 2.5 divisions from the left edge of the screen or vice versa shall be recorded as Gauge Corner Cracking (GCC) and not as OBS"

Checking the function and sensitivity of probes


(a) Normal probe:


The equipment shall be able to detect 5 mm dia. hole at the web-foot junction of the standard rail. The amplitude of the flaw echo shall be adjusted to 3 div. i.e. 60% of full screen height by the adjustment of gain knob of USFD. (Position of potentiometer knobs in the junction box should be set at 50% rotation).

(b) Angle probe 70º (forward & backward).

The equipment shall be able to detect 12 mm dia. hole for need based and 5 mm dia. hole for conventional criteria in the head portion of the standard rail as shown in Fig. 3 and 4 respectively by both forward and backward probes. The amplitude of the flaw shall be set to 3 div. i.e. 60% of screen height. This adjustment shall be done by individual potentiometer provided in the junction box.
(c) Gauge face corner 70° (forward & backward).

The equipment shall be able to detect 5 mm dia.FBH hole for need based criteria in the head portion of the standard rail made by use of suitable machine(electron drilling machine) as shown in Fig. 3 by both forward and backward probes. The amplitude of the flaw shall be set to 3 div. i.e. 60% of screen height. This adjustment shall be done by individual potentiometer provided in the junction box.

Classification of Rail Failure:


While testing of rails the rail flaws detected were classified into 2 types:


1. IMR Defects.                                                               2.OBS Defects

Rail Testing Frequency: (As per USFD Manual Cs.no 2)


Single rail tester :
Single rail tester is capable of testing only one of the rails at a time and is provided with five probes i.e. 0º , 70º Forward (F), 70ºBackward (B)central probes and, 70º Forward (F) and 70º Backward (B) gauge face corner. The normal probe (0º) is utilised for the purpose of detecting horizontal defects situated in head, web or foot. The 70º probe has been specifically provided for detecting defects in the rail head, the most typical of which is the transverse fissure or kidney fracture. 37º probes have been provided to find out defects originating from the bolt hole (star cracks). The approximate coverage of the rail section with the help of the above arrangement is indicated. The signal received from the defects by any of the above probes is indicated on the cathode ray tube (CRT) screen. In order to find out the origin of detection i.e. which probe has picked up the defect, provision for eliminating the individual probe operation has been made in the equipment.

Double Rail tester:
The double rail tester is capable of testing both the rails at a time. However, for each rail only three probes have been provided for the present i.e. 0º, 70º Forward and 70º Backward. This equipment, unlike the single rail tester, has multichannel facility i.e. the signal received from each probe can be instantaneously distinguished without taking recourse to process of elimination. This equipment has also been provided with a threshold arrangement, LED display and audio alarm in addition to the CRT screen. Thus there are three modes of defect indication i.e., CRT, audio alarm and LED display. The normal probe is provided for detection of horizontal defects and 70° probes have been provided for transverse defects in the head. For detection of bolt hole defects, the equipment works on the principle of back wall drop, which in the event of a bolt hole crack shows reduction in echo-amplitude of the back wall. It is also supported by separate audio alarm with distinctly different tone and LED display.

The introduction of double rail tester has been specifically made for enhancing the productivity of testing and as well as improving the quality and accuracy of flaw detection. Due to pre-calibrated arrangement, frequent setting of the equipment is not considered necessary.

Due to frequent misalignment of probes on the fish plated joints and limitations of detection of bolt hole cracks having unfavorable orientation and size, it is desirable to deploy double rail testers on LWR/CWR sections. It is desirable to deploy only the ultrasonic machine of the “single rail tester” for testing sections other than LWR/CWR.

Action to be taken after Detection of defects:

 Following action shall be taken in respect of defective rails & welds.

Register of Rail failures –
 All the cases of rail failures have to be entered in thesection register by the Permanent Way Inspector as laid down in. For this purpose all
failures whether in running lines, points and crossing rails etc. and irrespective of
type and age of the rails, have to be entered in the section register. This record is
intended to serve as a basic record which should be available in the office of the
Permanent Way Inspectors and will serve to furnish data, if required subsequently for
any statistical analysis or for framing out proposals for track renewal works. Care
should therefore be taken by the Permanent Way Inspectors for filling up all the
details. The Assistant Engineer concerned shall call for the P. W. Is register once
every year and initial the same in token of his perusal.

Reports of Rail failures –
 In addition to the records maintained in the section register, as detailed above, a report has to be prepared as per Annexure 2 / 10 in all cases of rail failures occurring in track with the exception of the cases noted below –

( a ) Rail failures occurring in non running lines.
( b ) Non standard and obsolete rails.
( c ) Rail removed due to casual renewals on account of accidental damages to the rails such as wheel burns and scabbings, buckling, kinks, derailments, abnormal slipping of loco wheels, excessive wear, loss of section by corrosion, battering, elongation of holes etc.
( d ) Machined rails such as mitred joints, switch expansion joints, switches and
crossings.

For this purpose, the Permanent Way Inspector will prepare a ‘Rail Failure’ Report in quadruplicate as per proforma at Annexure 2 / 10 and shall forward 3 copies to the Assistant engineer, who will transmit all the copies with his remarks to Divisional Engineer, for onward transmission of one copy each to the Chief Engineer and Executive Director ( M & C ) / RDSO / Lucknow. In case of failures requiring metallurgical investigation, the report should be prepared in quintuplicate, the extra copy being sent to the Chemist and metallurgist of the Zonal Railway along with the samples as detailed in the sub – para ( 7 ) below. Efforts should be made y Divisional Engineer so that the report reaches the Executive Director ( M & C ) / RDSO within a fortnight of the rail failure. Sketches illustrating the fractures will be prepared and submitted with the failure reports on each case, care being taken that the running face of the rail indicated thereon. It is particularly essential to record the type of failure in the failure reports against item No. 5.3 as per R.D.S.O. monograph ‘’Rail Failures – Description, Classification and Reporting’’. 

The Executive Director ( M & C ) will arrange to carry out analysis of rail failures from the reports received from the Permanent Way Inspectors and the Chemist and Metallurgist and publish reports with suggestions for reducing failures. In most cases, it is possible to determine the cause of the failure by visual examination / ultrasonic detection without the need for metallurgical investigation. However, in cases mentioned in sub – para ( 5 ) below, it is obligatory to take up full metallurgical examination by the Chemist and Metallurgist of the Railway concerned with a view to ascertaining the exact cause of failure. In such cases the rail failure report should be made out in the prescribed proforma inserting the most probable code of failure against item No. 5.3 and indicating whether the sample has been sent to the Chemist and Metallurgist for metallurgical investigation. 

For the cases of rail failures detected visually a short piece of rail approximately 1 meter long ( 500 mm + 500 mm ) has to be sent to the Zonal Railway’s Chemist and Metallurgist by the Permanent Way Inspector direct, along with a copy of the rail failure report, only for such cases which come under the category listed in sub para ( 5 ) below. In other cases, i.e. those detected by ultrasonic flow detectors, the rail pieces of 1 meter long ( 500 mm + 500 mm ) containing the flaw shall be sent for metallurgical test only from those rails which are removed from track based on the criteria for removal of rails and falling in the category listed in sub – para ( 5 )below. The test pieces for metallurgical examination are to be sent only for rail failures which occur within test free period subject to maximum of 10 years of rolling and for which detailed reports are to be prepared. In case of repetitive failures of rails of same rolling mark, irrespective of the type of fracture / flaw, short rail piece of approximately 1 meter ( 500 + 500 mm ) containing the fracture / flaw detected visually or by ultrasonic flaw detector should be sent to the Chemist and Metallurgist together with a rail failure report for Metallurgical investigation. Chief Track Engineer of Zonal railway shall forward the case of repetitive failure of rails of same rolling mark on account of Chemical & Metallurgical reasons to Executive Director / M & C / RDSO along with investigation reports from Chemist and Metallurgist. The rail pieces of approximately 1 meter ( 500 + 500 mm ) containing the fracture should be sent to Executive Director / M & C / RDSO together with a rail failure report for Metallurgical investigation where rail / weld failure is prima facia cause of train accident. To sum up, before sending the test pieces to the Chemist and Metallurgist or RDSO, it should be ensured that –

( I ) The rail failure is within test free period subject to maximum of 10 years of rolling of rail, irrespective of the type of fracture / flaw.

( ii ) The rail have been removed from track as a result of visual or ultrasonic detection and rail failure falls in categories listed in sub para ( 5 ) below.

( iii ) The rail where rail / weld failure is prima facie cause of train accident should be sent to RDSO.

( iv ) The rails with repetitive failure of same rolling mark irrespective of type of
failure.

In cases of failures of imported rails occurring within guarantee period, stipulation of sub para ( 6 ) shall be followed.

Para 257 ( 6 ) – Failure of imported rails within the Guarantee period – In all cases of failure of imported rail occurring within the guarantee period, irrespective of the type of fracture / flaw rail piece approximately 1 meter ( 500 + 500 mm ) containing the fracture / flaw detected visually or by ultrasonic flaw detector should be sent to the Chemist and Metallurgist together with a rail failure report for metallurgical investigation. 

Para 257 ( 7 ) – Procedure for sending samples for metallurgical investigation – In case of fractured rail, both the pieces of approximately 500 mm long each i.e. total 1 meter long containing fractured faces / flaw should be sent to the Chemist and Metallurgist for investigation. To avoid damage in transit, the fractured faces shall be protected with mineral jelly and suitably covered with hessian cloth. Cracked rails may also be suitably protected at the crack location to avoid damage in transit. Pieces having internal defects may be dispatched as such. The Chemist and Metallurgist of the Railway will carry out metallurgical investigation, as required, and forward one copy of the report each to the Chief Engineer of the Railway and the Executive Director ( M & C ) / RDSO. In case of failures of imported rails within the guarantee period, attributable to manufacturing defects as revealed by metallurgical investigation, the Chief Engineer should immediately lodge a provisional claim with the manufacturer pending Executive Director ( M & C )’s confirmation of the findings submitted by the Chemist and Metallurgist of the Railway.

The Executive Director ( M & C ) / RDSO will scrutinize the report submitted by the Chemist and Metallurgist and if he agrees with the findings as submitted inform the Chief Engineer accordingly. Where the Executive Director ( M & C ) / RDSO feels the need for carrying out further investigation before giving his verdict, he will call For the sample from the Chemist and Metallurgist of the railway and carry out confirmatory tests, as necessary and intimate the findings to the Chief Engineer. On The basis of Executive Director ( M & C )’s advice the Chief Engineer will then finalise the claim with the manufacturer.

In case of failures of rails other than imported, the Executive Director ( M & C )
RDSO will call for samples from the Chemist and Metallurgist for confirmatory tests, where necessary. Based on the trend indicated by the numerical analysis of the rail failures for the period under review the Executive Director ( M & C ) will bring to the notice of the indigenous manufacturers and Inspecting Agency, any
predominance of failure attributable to manufacturing defects, to enable corrective action being taken. (as per cs no.122 dated /11/10)

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.

Index -

01. INTEGRATED CONCEPT AND OBJECTIVES OF MATERIALS MANAGEMENT (1) 01.02 रेलपथ निरक्षक तथा सहायक मंडल अभियंता के कर्तव्य (1) 02 रेलपथ (1) 02. ORGANIZATION OF MATERIALS MANAGEMENT DEPARTMENT (1) 02.01 90 यूटीएस रेलों के सम्भाल (1) 02.04 रेल तापमान (1) 02.05 रेल जोड (1) 03 स्लीपरो के कार्य (1) 03. CLASSIFICATION/CODIFICATION NOMENCLATURE OF STORES ON INDIAN RAILWAYS (1) 03.01 विभिन्न प्रकार के स्लीपरो की तुलना (1) 03.02 लचीले बंधन (1) 03.03 स्लीपर बिछाना (1) 04. PLANNING OF NON-STOCK ITEMS AND PROCESSING OF REQUISITION (1) 04.01 ट्रैक के लिए बैलास्ट प्रोफाइल (1) 04.02 फार्मेशन (1) 04.03 ब्रिज (पुल) (1) 05 पाइंट्स तथा क्रासिंग - परिचय एवं परिभाषाए (1) 05 PLANNING OF STOCK ITEMS & SYSTEMS OF RECOUPMENT (1) 05.01 विषेश ले आउट (1) 05.02 पृथक्रकरण (आइसोलेशन ) (1) 05.03 तथा क्रासिंग का अनुरक्षण तथा निरक्षण (1) 05.04 पॉइंट्स एवं क्रासिंग की (1) 06 गोलाई का प्ररंभिक ज्ञान (1) 06 PURCHASE POLICY (1) 06.01 वर्को का पुनः संरेखण (1) 07 Purchase Procedure on zonal Railways (1) 08 TENDER EVALUATION AND MISCELLANEOUS POLICY ISSUES IN PURCHASES (1) 08.01 व्यव्स्तिथ ओवरहालिंग (1) 08.02 रेलपथ अनुरक्षण का वार्षिक कार्यक्रम (1) 08.04 गहरी छनाई (1) 08.04.1 रेलपथ का उठाना लोवेरिंग तथा क्रीप (1) 08.05 छोटी वेल्डेड रेल ( एसडब्लूआर ) (1) 08.06 आन ट्रैक मशीन (1) 08.07 छोटी ट्रैक मशीने (1) 08.09 विद्युतीकृत सेक्शन में हाइट गेज (1) 08.11 अंडर ट्रायल सामग्री का रिकॉर्ड (1) 09 गति प्रतिबन्ध और संकेतक (1) 09 Receipt And Inspection of stores (1) 09.01 ठेकेदार की सुरक्षित कार्य प्रणाली (1) 09.03 रेल संरक्षा आयुक्त की स्वीकृति वाले कार्य (1) 10 निरक्षण का उद्देश्य (1) 10 ISSUE AND DISTRIBUTION OF STORES (1) 10.01 राइडिंग गुणवत्ता तथा राइडिंग इंडेक्स (1) 10.03 सिटीआर तथा टीजीआई (1) 10.04 रेलपथ प्रबंधन पध्दति (टीऍमएस ) (1) 11 RETURNED STORES (1) 11.01 स्लीपरो का बिछाना (1) 12 दुर्घटना (1) 12 Scrap Disposal (1) 12.01 ब्रीच (1) 12.02 डाईवर्शन (1) 13 INVENTORY MANAGEMENT (1) 14 लंबी वेल्डित रेल (परिभाषाए) (1) 14.01 एलडब्लूआर / सीडब्लूआरके लिये स्वीकृत स्थान (1) 14.02 एलडब्लूआरकी डीस्ट्रेसिंग (1) 14.03 एलडब्लूआर / सीडब्लूआर का अनुरक्षण (1) 14.04 रेलपथ पर्येवेक्षक - मेट तथा चाबीदार के लिए अनुमत तथा निषिद्ध कार्य (1) 15 - सर्वेक्षण (1) 15 बयाना राशि और जमानत राशि (1) 15.01 SURVEYING (2) 16 रेलवे टेंडर सिस्टम (Railway Tender System) (1) Accidents (2) Active & Passive Earth Pressure (1) Anti corrosive treatment (1) Ballast (2) Bearings in Bridge (1) Blanketing Material (1) Bridges (2) Buckling of track (1) Building Work (1) Cant deficiency & Cant Excess (1) Census (1) Chequered Tiles (1) Chlorination of Water (2) Chlorination Practices (1) Chlorine demand (1) Civil Engineering - Bridges (2) Civil Engineering - P Way (40) Civil Engineering - Works (5) CMS Crossing (1) Completion report (1) Contour & Contour interval (1) Correction Slip (1) CRS Sanction (1) CTR and TGI Value (1) Curing of Concrete (1) curves (2) Deep Screening (2) Design mode (1) Design of concrete mix (2) Destressing (1) Disinfection of water (1) disposal of human waste: (1) Distressed bridges (2) Distressing of LWR (2) distribution System (1) dry density (1) Duties (3) Duties & Responsibilities (9) Duties of Gateman (1) E01.02 Duties of Keyman / Mate / PWS (1) E02.01 Permanent Way (1) E02.02 Handling of 90 UTS rails (1) E02.05 Rail Temperature (1) E02.06 Rail Joints (1) E02.07 Maintenance of Rail Joints (1) E03.01 SLEEPERS AND FASTENINGS - Functions of Sleepers (1) E03.02 Comparison between Various Types of Sleepers (1) E03.04 Laying of Sleepers (1) E04.02 Ballast Profile for L.W.R. track (1) E04.04 Bridges (1) E05.01 Points & Crossings: Introduction & Definitions (1) E05.04 Maintenance and Inspection of Points and Crossing (1) E05.05 Reconditioning of Points and Crossing (1) E06.01 Basics of Curves (1) E06.02 Realignment of Curve (1) E08.01 MAINTENANCE OF TRACK-Through packing (1) E08.02 Systematic Overhauling (1) E08.03 Annual Programme for Regular Track Maintenances (1) E08.04 Lifting/ Lowering of Track and Creep (1) E08.05 Deep Screening (1) E08.06 Short Welded Rail (1) E08.07 Maintenance of SWR (1) E08.10 Level Crossing (1) E08.11 Equipments at Level Crossing (1) E08.12 Maintenance / Examination / Inspection of Level Crossing / Gate (1) E08.14 Welding of Rails (1) E08.15 Records of Material under Trial (As per Cs.no 99) (1) E09.01 Speed Restriction and Indicators (1) E09.02 Safe Working of Contractors (As per Cs.No 95) (1) E09.03 Works Requiring CRS Sanction (1) E10.01 INSPECTION OF TRACK - Object of Inspection (1) E10.02 Riding Quality and Riding Index (1) E10.03 Track Recording and Oscillograph Car (1) E10.04 CTR and TGI Value (1) E12.01 ACCIDENTS AND BREACHES - Accidents (1) E12.02 Breaches (1) E12.03 Diversion (1) E14.01 LONG WELDED RAIL - Definitions (1) E14.02 Permitted locations for LWR/CWR (1) E14.04 Maintenance of LWR / CWR (1) E14.05 DOs and Don’ts OF LWR For PWM / MATES & KEYMAN (1) Egineering (1) Elastic Fastening (1) Elastic Rail Clip (1) Encroachments of Railway land. (2) Engineering (26) Engineering - Book (3) Examination of Rails (2) Fabrication of Glued joint IN SITU. (1) Flushing cisterns (1) FOB (1) Gateman (2) Greasing of ERCs (1) Grow More Food Scheme (1) Guideline (3) H02 भण्डार विभाग का महत्व (1) H03 भण्डार डिपो की संरचना (1) H04 भण्डार का वर्गीकरण (1) H05 कोडिफीकेशन (1) H06 मानकीकरण एवं उसकी उपयोगिता (1) H07 वित्तीय औचित्य के सिध्दांत (1) H08 क्रय के विभिन्न माध्यम (1) H09 क्रय में विविध अधिमान्यताए (1) H10 भण्डार विभाग के अधिकारियो की क्रय शक्तियां (1) H12 निविदा समिति (1) H13 अनुबंध (1) H16 स्थानीय खरीद (1) H17 भण्डार डिपो में भण्डार प्राप्ति के स्त्रोत (1) H18 महत्वपूर्ण वस्तुए एवं उनकी खरीद (1) H19 भण्डार डिपो का संगठन एवं कार्य (1) H20 प्राप्ति अनुभाग की क्रिया - विधि (1) H21 वार्ड की क्रिया - विधि (1) H22 प्रेषण अनुभाग की क्रिया - विधि (1) H23 बहीखाता अनुभाग की क्रिया - विधि (1) H24 डिपो प्रणाली (1) H25 भण्डार का निरीक्षण (1) H26 अस्वीकृत भण्डार (1) H27 लौटाया गया भण्डार (1) H28 अग्रदाय भण्डार (1) H29 अधिशेष भण्डार (1) H30 रेल सामग्री की बिक्री (1) H31 रद्दी माल और नीलामी बिक्रिया (1) H32 वस्तु - सूची नियंत्रण (1) H33 स्टॉक सत्यापन (1) H34 मांगकरताओ व्दारा डिपुओ से भण्डार प्राप्त करने की प्रक्रिया (1) H35 संक्षिप्त टिप्पणीयां (1) Handling of 90 UTS Rails (1) Height Gauges on Electrified Section (1) Honey combing of concrete & its prevention (1) Hot Weather Patrolling (1) Imprest Store (1) INDEX (2) Indicator Boards & Signages (1) Inspection (6) Insulated joints (1) Isolation (1) Keyman / Mate / PWS (3) Laying of Sleepers (1) LDCE Exam (3) Level Crossing (2) Level crossings (2) Licensing Railway Land cultivation (1) Liner Biting (1) LWR (6) Maintenance (2) Maintenance in Electrified Area (2) Maintenance of CMS Xing (1) Maintenance of P Way (5) Maintenance of Rail Joints (1) Maintenancee of SWR (1) Manson precaution (1) Monsoon Patrolling (2) Numerical rating system (NRS) (1) Optimum moisture content (1) P Way (23) Pandrol Clip (1) pass (1) Patrolling of Rail Permanent Way (6) Permanent Way (2) Permanent Way (P Way) (10) Pile Foundation (1) Points and Crossing (3) Protection of Rail (1) Pumping Water Level (1) PWI (1) PWI / AEN / DEN (1) quality control (2) Question & Answer (62) Rail Clusters (1) Rail Formation (2) rail fracture (1) Rail Joints (1) Rail Renewal (3) Rail Welding (3) Rails Defects (2) Railway Affecting Works (1) Railway Construction (1) Railway Organisation (2) Realignments of Curve) (1) Reconditioning of Points and Crossing (1) Rehabilitation of Bridges (1) Renewal of Rail (1) River Training protection work (1) safe speed (1) Safe Working (1) Safety at P. Way Work Site (1) Schedule of Inspection of Bridges (1) Short Note - Bridge (8) Short Note - P Way (48) Short Note - Works (35) Short Notes - Mislanious (7) Sleeper (4) Sleeper Cribs (1) Soil Consistency (1) Special Layouts (2) Speed Restriction and Indicators (2) Static Water Level (1) Steel Structures (1) Stock sheet (1) Store (34) super elevation (1) Tender System (1) Testing of Rails (2) TGI and OMS (1) Thermit Welding (1) Through Parking (2) Tiles (2) Track Circuited Areas (2) Track Inspection (1) Track Machines (6) Track Management System (1) Track Tolerances (2) track-Overhauling (1) Transitions (1) Turnout (1) urinals (1) USFD (2) Venerable location (1) VIDEO (2) wash basin. (1) Washable Aprons (1) Water Cement ratio (1) Water closetsu (1) Water Quality (1) Water Supply (1) Waterproofing (1) weld failure (1) Well Foundation (1) Winter Precautions (1) Workability of Concrete (1) Working of Contractors (2) works (9) कार्य एवं उद्देश्य (1) ट्रैक रिकॉर्डिंग तथा दोलन लेखी कार (1) रेल पथ मेट के कर्तव्य (1)