1.Which of the statements with regard to formation is correct
(1) One of the Functions of the formation is to facilitate drainage
(2) Width of bank for double railway line is 12.155 meters
(3) Width of cutting for double railway track is 11.750 meters
(4) Centre to centre of formation for double line is 4.725 meters
(5) Width of formation is different for concrete sleeper track and other than concrete sleeper track
a) 2, 3, 5
b) 3, 4, 5* 
c) 2, 3, 4 
d) 2, 4, 5 
Answer - b) 3, 4, 5* 

2. Centre to Centre spacing of formation for double railway line for Broad Gauge is
a) 1676 mm
b) 4725 mm
c) 4265mm
d) 5300 mm*
Answer - d) 5300 mm*

3. Earthwork in embankment for railway with manual compaction should be done in layers not exceeding--------------
a) 15 centimeter
b) 20 centimeters
c) 25 centimeters 
d) 30 centimeters*
Answer - d) 30 centimeters*

4. To provide inverted filter to improve the bearing capacity of soil the liquid limit of blanketing material should not be greater than
a) 5 
 b) 20 
 c) 27 
d) 35*
Answer -  d) 35*

5. To provide inverted filter to improve the hearing capacity of soil the plasticity index of blanketing material should not be greater than
a) 15* 
b) 20 
c) 27
d) 35 
Answer - a) 15* 

6. The bottom of side drains should be below the formation level by at least------------
a) 45 cm
b )30 cm*
c) 15 cm
d) 60 cm
Answer - b )30 cm*

7. Cross slope of the formation to have good drainage of Ballast section is 
a) 1 in 40* 
b) 1 in 50 
c) 1 in 30 
d) 1 in 20 
Answer - a) 1 in 40* 

8. The side slope of formation in embankment is
a) 2 : 1*
b) 1: 1 
c) 1:5
d) 1:3 
Answer -  a) 2 : 1*

9. The side slope of formation in embankment /cutting depends on
a) Shearing strength of soil and its angle of repose* 
b) Angle of repose
c) Bearing capacity of the soil 
 d) Optimum moisture content of the soil
Answer - a) Shearing strength of soil and its angle of repose* 

10. The recommended width of Double line cutting formation for B G is
a) 10210 mm
b) 10 975 mm
c) 11555 mm*
d) 10 820 mm
Answer - c) 11555 mm*

11. The recommended width of Single line formation cutting for BG excluding drain is
a) 6250 mm*
b) 6850mm
c) 54 90mm
d) 6100mm 
Answer - a) 6250 mm*

12. In case of compaction of soil by sheep foot roller maximum thickness of layer should not exceed buy more than -------------- centimeter of length of their teeth
a) 5 centimeter*
b) 4 centimeter
c) 3 centimeter 
d) 2 centimeter
Answer -  a) 5 centimeter*

13. The catch water drains are provided in the
a) Formation in the embankment
b) Formation in cutting*
c) Zero fills formation
d) Steep gradient
Answer - b) Formation in cutting*

14. Cross sectional area of catch water drain should not be more than 
a) 0 .75 square meter*
b) 0. 90 square meter
c) 0. 80 square meter
d). 50 square meter
Answer - a) 0 .75 square meter*

15. Density of each compacted layer should be ascertained by taking soil samples on either side of Central Line at
a) 5 meter interval 
b) 10 meter interval*
c) 12 meter interval 
d) 15 meter internal
Answer - b) 10 meter interval*

16. For laying a Railway track the prepared surface ready to receive the ballast is called 
 a) Sub ballast
b) Formation*
c) Blanket 
d) Cushion 
Answer - b) Formation*

17. The height of formation depends upon the
a) Ground contours and the gradient adopted*
b) Ground contour only 
c) Gradient adopted only
d) Rainfall intensity over the year
Answer -  a) Ground contours and the gradient adopted*

18. The dry density of soil is
a) Always greater than the saturated density
b) Weight of soil solids per unit of total volume prior to drying* 
c) Total weight of soil solids per unit of its total volume 
d) Total weight of soil mass per unit of its total volume
Answer - b) Weight of soil solids per unit of total volume prior to drying* 

19. The ratio of volume of water present in a given soil sample to the total volume of voids in it is known as
a) Percentage of air voids 
b) Degree of saturation *
c) Void ratio
d) Porosity
Answer - b) Degree of saturation *

20. The ratio of volume of air voids to the volume of voids is known as
a) Percentage of air voids
b) Porosity
c) Degree of saturation
d) Air content*
Answer - d) Air content*

21. At the liquid limit 
a) The soil just begins to crumble when rolled into a thread
b) The shearing strength against flowing is negligible 
c) The shearing strength against flowing is a small but definite*
d) The soil will not get fully saturated
Answer - c) The shearing strength against flowing is a small but definite*

22. The property of soil which allows it to be deformed rapidly, without rupture, without elastic rebound and without volume change is known as
a) Porosity 
b) Plasticity* 
c) Stiffness 
d) Plastic limit
Answer -  b) Plasticity* 

23. The minimum water content in soil at which the soil just begins to crumble when rolled into threads 3 mm in diameter is known as
a) Plastic limit
b) Liquid limit 
c) Consistency limit 
d) Shrinkage limit
Answer - 

24. The minimum water content at which a reduction in water content will not cause a decrease in the volume of a soil mass is known as
a) Plastic limit
b) Shrinkage limit*
c) Liquid limit 
d) Consistency limit 
Answer -  b) Shrinkage limit*

25. The numerical difference between the liquid limit and plastic limit of a soil is known as
a) Liquidity index 
b) Plasticity index *
c) Shrinkage index
d) Consistency index 
Answer -   b) Plasticity index *

26. In India soils are classified by 
a) MIT classification
b) Unified soil classification system*
c) International classification system 
d) Particle size classification
Answer -    b) Unified soil classification system*

27. The consistency index of soil is
a) (Natural water content - liquid limit) / plasticity index 
b) (Natural water content - liquid limit )/ liquidity index
c) (Liquid limit - natural water content)/ consistency index
d) (Liquid limit - natural water content)/plasticity index*
Answer -  d) (Liquid limit - natural water content)/plasticity index*

28. The property of a soil due to which water percolates through it is known as 
a) Porosity
b) Permeability*
c) Moisture content 
d) Capillarity
Answer - b) Permeability*

29. Permeability of soil varies
a) Inversely as square of grain size
b) Inversely as grain size
c) Directly as grain size 
d) Square of grain size*
Answer - d) Square of grain size*

30. Quicksand is
a) Moist sand containing a small percentage of clay 
b) Is a condition which generally occurs in coarse sands
c) Is a condition in which cohesive properties of soil increase rapidly 
d) Is a condition in which a cohesion less soil loses its strength because of upward flow of water*
Answer - d) Is a condition in which a cohesion less soil loses its strength because of upward flow of water*

31. Piping in a soil mass is
a) Erosion of subsoil by the high velocities of flow of water through it when such velocities exceed a certain limit*
b) Caused due to very low exit gradient
c) Due to continuous passage of water through a series of well connected pores
d) Due to loss of the strength of cohesion less soil because of upward flow of of water 
Answer - a) Erosion of subsoil by the high velocities of flow of water through it when such velocities exceed a certain limit*

32. The maximum dry density to which a soil may be compacted to depends upon 
a) Soil water content *
b) The process of compaction 
c) The voids ratio 
d) Is independent of the type of soil 
Answer - a) Soil water content *

33. A saturated clay is to be tested for shearing strength. Which test should be recommended?
a) Direct shear test
b) Triaxial shear test
c) Vane shear test 
d) Unconfined compression*
Answer -  d) Unconfined compression*

34. A temporary enclosure in a river or Lake built around a working area for the purpose of excluding water during construction is known 
a) Caisson
b) Augur
c) Cofferdam *
d) Sheet pile wall
Answer - c) Cofferdam *

35. The maximum pressure which the soil can carry safely without the risk of shear failure is called 
a) Safe bearing capacity 
b) Ultimate bearing capacity*
c) Allowable bearing capacity 
d) Shear bearing capacity
Answer - b) Ultimate bearing capacity*

36. Black cotton soils are
a) Heavy clay soils varying from clay to Loam, with clay content of 40 to 50% formed by decomposition of rocks by long continued weathering*
b) Compacted and laminated clays
c) Soils containing carbon of coal underneath
d) Dark brown earthy materials formed due to partial or complete decomposition of vegetable matter 
Answer -  a) Heavy clay soils varying from clay to Loam, with clay content of 40 to 50% formed by decomposition of rocks by long continued weathering*

37. The high density of soil placed in a fill is desired in order to
a) Increase its shear resistance*
b) Reduce its shear resistance
c) Promote future settlements
d) Decrease percolation through the fill. 
Answer - a) Increase its shear resistance*

38. Plasticity index represents the range of water content between 
a) Liquid and plastic limit *
b) Plastic limit and semi solid limit
c) Semisolid Limit and liquid limit
d) Liquid limit and solid limit. 
Answer - a) Liquid and plastic limit *

39. For yard drainage Pucca drains should be designed for the velocity of
a) 0 05 to 1 meter per second 
b) 1 to 1.5 meter per second 
c) 1.5 to 2 meter per second 
d) 2 to 2.5 meter per second
Answer -  

40. Formation prepared by depositing Soil over the existing ground level is known as 
a) Formation in cutting 
b) Formation in embankment 
c) Zero fills formation 
d) Natural formation
Answer - 

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.

Index -

01. INTEGRATED CONCEPT AND OBJECTIVES OF MATERIALS MANAGEMENT (1) 01.02 रेलपथ निरक्षक तथा सहायक मंडल अभियंता के कर्तव्य (1) 02 रेलपथ (1) 02. ORGANIZATION OF MATERIALS MANAGEMENT DEPARTMENT (1) 02.01 90 यूटीएस रेलों के सम्भाल (1) 02.04 रेल तापमान (1) 02.05 रेल जोड (1) 03 स्लीपरो के कार्य (1) 03. CLASSIFICATION/CODIFICATION NOMENCLATURE OF STORES ON INDIAN RAILWAYS (1) 03.01 विभिन्न प्रकार के स्लीपरो की तुलना (1) 03.02 लचीले बंधन (1) 03.03 स्लीपर बिछाना (1) 04. PLANNING OF NON-STOCK ITEMS AND PROCESSING OF REQUISITION (1) 04.01 ट्रैक के लिए बैलास्ट प्रोफाइल (1) 04.02 फार्मेशन (1) 04.03 ब्रिज (पुल) (1) 05 पाइंट्स तथा क्रासिंग - परिचय एवं परिभाषाए (1) 05 PLANNING OF STOCK ITEMS & SYSTEMS OF RECOUPMENT (1) 05.01 विषेश ले आउट (1) 05.02 पृथक्रकरण (आइसोलेशन ) (1) 05.03 तथा क्रासिंग का अनुरक्षण तथा निरक्षण (1) 05.04 पॉइंट्स एवं क्रासिंग की (1) 06 गोलाई का प्ररंभिक ज्ञान (1) 06 PURCHASE POLICY (1) 06.01 वर्को का पुनः संरेखण (1) 07 Purchase Procedure on zonal Railways (1) 08 TENDER EVALUATION AND MISCELLANEOUS POLICY ISSUES IN PURCHASES (1) 08.01 व्यव्स्तिथ ओवरहालिंग (1) 08.02 रेलपथ अनुरक्षण का वार्षिक कार्यक्रम (1) 08.04 गहरी छनाई (1) 08.04.1 रेलपथ का उठाना लोवेरिंग तथा क्रीप (1) 08.05 छोटी वेल्डेड रेल ( एसडब्लूआर ) (1) 08.06 आन ट्रैक मशीन (1) 08.07 छोटी ट्रैक मशीने (1) 08.09 विद्युतीकृत सेक्शन में हाइट गेज (1) 08.11 अंडर ट्रायल सामग्री का रिकॉर्ड (1) 09 गति प्रतिबन्ध और संकेतक (1) 09 Receipt And Inspection of stores (1) 09.01 ठेकेदार की सुरक्षित कार्य प्रणाली (1) 09.03 रेल संरक्षा आयुक्त की स्वीकृति वाले कार्य (1) 10 निरक्षण का उद्देश्य (1) 10 ISSUE AND DISTRIBUTION OF STORES (1) 10.01 राइडिंग गुणवत्ता तथा राइडिंग इंडेक्स (1) 10.03 सिटीआर तथा टीजीआई (1) 10.04 रेलपथ प्रबंधन पध्दति (टीऍमएस ) (1) 11 RETURNED STORES (1) 11.01 स्लीपरो का बिछाना (1) 12 दुर्घटना (1) 12 Scrap Disposal (1) 12.01 ब्रीच (1) 12.02 डाईवर्शन (1) 13 INVENTORY MANAGEMENT (1) 14 लंबी वेल्डित रेल (परिभाषाए) (1) 14.01 एलडब्लूआर / सीडब्लूआरके लिये स्वीकृत स्थान (1) 14.02 एलडब्लूआरकी डीस्ट्रेसिंग (1) 14.03 एलडब्लूआर / सीडब्लूआर का अनुरक्षण (1) 14.04 रेलपथ पर्येवेक्षक - मेट तथा चाबीदार के लिए अनुमत तथा निषिद्ध कार्य (1) 15 - सर्वेक्षण (1) 15 बयाना राशि और जमानत राशि (1) 15.01 SURVEYING (2) 16 रेलवे टेंडर सिस्टम (Railway Tender System) (1) Accidents (2) Active & Passive Earth Pressure (1) Anti corrosive treatment (1) Ballast (2) Bearings in Bridge (1) Blanketing Material (1) Bridges (2) Buckling of track (1) Building Work (1) Cant deficiency & Cant Excess (1) Census (1) Chequered Tiles (1) Chlorination of Water (2) Chlorination Practices (1) Chlorine demand (1) Civil Engineering - Bridges (2) Civil Engineering - P Way (40) Civil Engineering - Works (5) CMS Crossing (1) Completion report (1) Contour & Contour interval (1) Correction Slip (1) CRS Sanction (1) CTR and TGI Value (1) Curing of Concrete (1) curves (2) Deep Screening (2) Design mode (1) Design of concrete mix (2) Destressing (1) Disinfection of water (1) disposal of human waste: (1) Distressed bridges (2) Distressing of LWR (2) distribution System (1) dry density (1) Duties (3) Duties & Responsibilities (9) Duties of Gateman (1) E01.02 Duties of Keyman / Mate / PWS (1) E02.01 Permanent Way (1) E02.02 Handling of 90 UTS rails (1) E02.05 Rail Temperature (1) E02.06 Rail Joints (1) E02.07 Maintenance of Rail Joints (1) E03.01 SLEEPERS AND FASTENINGS - Functions of Sleepers (1) E03.02 Comparison between Various Types of Sleepers (1) E03.04 Laying of Sleepers (1) E04.02 Ballast Profile for L.W.R. track (1) E04.04 Bridges (1) E05.01 Points & Crossings: Introduction & Definitions (1) E05.04 Maintenance and Inspection of Points and Crossing (1) E05.05 Reconditioning of Points and Crossing (1) E06.01 Basics of Curves (1) E06.02 Realignment of Curve (1) E08.01 MAINTENANCE OF TRACK-Through packing (1) E08.02 Systematic Overhauling (1) E08.03 Annual Programme for Regular Track Maintenances (1) E08.04 Lifting/ Lowering of Track and Creep (1) E08.05 Deep Screening (1) E08.06 Short Welded Rail (1) E08.07 Maintenance of SWR (1) E08.10 Level Crossing (1) E08.11 Equipments at Level Crossing (1) E08.12 Maintenance / Examination / Inspection of Level Crossing / Gate (1) E08.14 Welding of Rails (1) E08.15 Records of Material under Trial (As per Cs.no 99) (1) E09.01 Speed Restriction and Indicators (1) E09.02 Safe Working of Contractors (As per Cs.No 95) (1) E09.03 Works Requiring CRS Sanction (1) E10.01 INSPECTION OF TRACK - Object of Inspection (1) E10.02 Riding Quality and Riding Index (1) E10.03 Track Recording and Oscillograph Car (1) E10.04 CTR and TGI Value (1) E12.01 ACCIDENTS AND BREACHES - Accidents (1) E12.02 Breaches (1) E12.03 Diversion (1) E14.01 LONG WELDED RAIL - Definitions (1) E14.02 Permitted locations for LWR/CWR (1) E14.04 Maintenance of LWR / CWR (1) E14.05 DOs and Don’ts OF LWR For PWM / MATES & KEYMAN (1) Egineering (1) Elastic Fastening (1) Elastic Rail Clip (1) Encroachments of Railway land. (2) Engineering (26) Engineering - Book (3) Examination of Rails (2) Fabrication of Glued joint IN SITU. (1) Flushing cisterns (1) FOB (1) Gateman (2) Greasing of ERCs (1) Grow More Food Scheme (1) Guideline (3) H02 भण्डार विभाग का महत्व (1) H03 भण्डार डिपो की संरचना (1) H04 भण्डार का वर्गीकरण (1) H05 कोडिफीकेशन (1) H06 मानकीकरण एवं उसकी उपयोगिता (1) H07 वित्तीय औचित्य के सिध्दांत (1) H08 क्रय के विभिन्न माध्यम (1) H09 क्रय में विविध अधिमान्यताए (1) H10 भण्डार विभाग के अधिकारियो की क्रय शक्तियां (1) H12 निविदा समिति (1) H13 अनुबंध (1) H16 स्थानीय खरीद (1) H17 भण्डार डिपो में भण्डार प्राप्ति के स्त्रोत (1) H18 महत्वपूर्ण वस्तुए एवं उनकी खरीद (1) H19 भण्डार डिपो का संगठन एवं कार्य (1) H20 प्राप्ति अनुभाग की क्रिया - विधि (1) H21 वार्ड की क्रिया - विधि (1) H22 प्रेषण अनुभाग की क्रिया - विधि (1) H23 बहीखाता अनुभाग की क्रिया - विधि (1) H24 डिपो प्रणाली (1) H25 भण्डार का निरीक्षण (1) H26 अस्वीकृत भण्डार (1) H27 लौटाया गया भण्डार (1) H28 अग्रदाय भण्डार (1) H29 अधिशेष भण्डार (1) H30 रेल सामग्री की बिक्री (1) H31 रद्दी माल और नीलामी बिक्रिया (1) H32 वस्तु - सूची नियंत्रण (1) H33 स्टॉक सत्यापन (1) H34 मांगकरताओ व्दारा डिपुओ से भण्डार प्राप्त करने की प्रक्रिया (1) H35 संक्षिप्त टिप्पणीयां (1) Handling of 90 UTS Rails (1) Height Gauges on Electrified Section (1) Honey combing of concrete & its prevention (1) Hot Weather Patrolling (1) Imprest Store (1) INDEX (2) Indicator Boards & Signages (1) Inspection (6) Insulated joints (1) Isolation (1) Keyman / Mate / PWS (3) Laying of Sleepers (1) LDCE Exam (3) Level Crossing (2) Level crossings (2) Licensing Railway Land cultivation (1) Liner Biting (1) LWR (6) Maintenance (2) Maintenance in Electrified Area (2) Maintenance of CMS Xing (1) Maintenance of P Way (5) Maintenance of Rail Joints (1) Maintenancee of SWR (1) Manson precaution (1) Monsoon Patrolling (2) Numerical rating system (NRS) (1) Optimum moisture content (1) P Way (23) Pandrol Clip (1) pass (1) Patrolling of Rail Permanent Way (6) Permanent Way (2) Permanent Way (P Way) (10) Pile Foundation (1) Points and Crossing (3) Protection of Rail (1) Pumping Water Level (1) PWI (1) PWI / AEN / DEN (1) quality control (2) Question & Answer (62) Rail Clusters (1) Rail Formation (2) rail fracture (1) Rail Joints (1) Rail Renewal (3) Rail Welding (3) Rails Defects (2) Railway Affecting Works (1) Railway Construction (1) Railway Organisation (2) Realignments of Curve) (1) Reconditioning of Points and Crossing (1) Rehabilitation of Bridges (1) Renewal of Rail (1) River Training protection work (1) safe speed (1) Safe Working (1) Safety at P. Way Work Site (1) Schedule of Inspection of Bridges (1) Short Note - Bridge (8) Short Note - P Way (48) Short Note - Works (35) Short Notes - Mislanious (7) Sleeper (4) Sleeper Cribs (1) Soil Consistency (1) Special Layouts (2) Speed Restriction and Indicators (2) Static Water Level (1) Steel Structures (1) Stock sheet (1) Store (34) super elevation (1) Tender System (1) Testing of Rails (2) TGI and OMS (1) Thermit Welding (1) Through Parking (2) Tiles (2) Track Circuited Areas (2) Track Inspection (1) Track Machines (6) Track Management System (1) Track Tolerances (2) track-Overhauling (1) Transitions (1) Turnout (1) urinals (1) USFD (2) Venerable location (1) VIDEO (2) wash basin. (1) Washable Aprons (1) Water Cement ratio (1) Water closetsu (1) Water Quality (1) Water Supply (1) Waterproofing (1) weld failure (1) Well Foundation (1) Winter Precautions (1) Workability of Concrete (1) Working of Contractors (2) works (9) कार्य एवं उद्देश्य (1) ट्रैक रिकॉर्डिंग तथा दोलन लेखी कार (1) रेल पथ मेट के कर्तव्य (1)