STORE - INVENTORY MANAGEMENT

13.1.0 Definition Of Inventory :

The Dictionary meaning of Inventory is 'a list of goods'. In a wider sense, inventory can be defined as an idle resource which has an economic value. It is however, commonly used to indicate various items of stores kept in stock in order to meet future demands.
  • In any organization, there may be following four types of inventory:
(a) Raw materials & parts-- These may include all raw materials, components and assemblies used in the manufacture of a product;

(b) Consumables & Spares -- These may include materials required for maintenance and day-to-day operation;

(c) Work in progress -- These are items under various stages of production not yet converted as finished goods;

(d) Finished Products -- Finished goods not yet sold or put into use.

13.1.1 Need For Inventory : Many of the items we need for our day-to-day maintenance and operation are required to be specially manufactured for the Railways. The time to procure these materials, therefore, is longer due to various reasons and it is not possible to procure these materials when instantaneously required. It is, therefore, necessary to keep stocks of such items.
  • Even for those items which are readily available in the market, it may not be economical to buy these items every time as buying in piecemeal involves additional costs to the administration. Therefore, we may find it cheaper to buy in bulk and to stock some of these items and supply our indentors through such stocks. 
  • There are always some fluctuations in demand as well as fluctuations in the time within which material can be procured. It is therefore, not possible to forecast our requirements exactly and time the purchases in such a way so that the materials will arrive just when they are physically required. It, therefore, becomes necessary to maintain stocks of these items.

13.1.2 Basic Problems of Inventory Management : From the above discussions, it will be seen that on the one hand inventories are idle and valuable resource i.e. capital remains locked up in the inventories which can be used for other productive purposes but on the other hand, they are desirable to satisfy manufacturing, maintenance or operation requirement of the organization. Hence basic problem of inventory management is to optimize the stock levels of different materials so that their stocks are maintained at optimum levels without affecting the production or day-to-day maintenance . Three basic problems associated with this optimization of stocks are ;

(a) When to initiate purchase of the materials

(b) How much quantities are to be purchased at a time and

(c) What should be the stock levels of different items.

  • For getting answers to these questions, we have to investigate various types of costs related to inventory management.

13.2.0 Various Costs Related To Inventory Management :

13.2.1 Costs Of Ordering Or Costs Of Acquisition : For a large organization, it becomes necessary to have a separate purchase office to purchase thousands of items. The demands received are technically scrutinized and for purchasing them, inquiries are issued, tenders are received and evaluated, orders are progressed, materials are received and inspected and lastly, the payments are arranged. All these mean additional costs to the organization. All these costs together constitute what is called cost of ordering or cost of acquisition.
  • In the Railways, we do not have a system of working out these costs. But it is necessary that for a given stores organization, total number of purchases are ascertained and average cost per purchase order worked out. When we work out the costs, we may find that some costs are fixed while some are variable. We should be interested in knowing the variable costs.
  • As we are using 3 major systems of purchasing viz., advertised tender, limited tender and cash purchase systems, it is advisable to work out the ordering costs for these three different procedures of purchasing.
  • Based on some of the studies made ordering costs may be as follows: 
  1. Cash Purchase Rs.50 to Rs.100 per purchase
  2. Limited Tender Purchase Rs.300 to Rs.600 "
  3. Advertised Tender Purchase Rs.1000 to Rs.2000 "
  • These are just approximate and may vary considerably depending upon various factors. It is repeated that every Railway should establish these costs from time to time so that they can be used in designing proper inventory models.
13.2.2 Inventory Carrying Costs : The very fact that the items are required to be kept in stock means additional expenditure to the organization. The different elements of costs involved in holding inventory are as follows:

(a) Interest on capital / cost of capital / opportunity costs : When materials are kept in stock money representing the value of materials is blocked. In a developing economy, capital is extremely scarce and as such, the real value of capital is much higher than the nominal rate of interest which the organization like Railways may be paying. The ,money which is blocked up is not available to the organization to do more business or to use it for alternative productive investment. This opportunity to earn more profits which we loose can be expressed asopportunity cost. o While working out the inventory carrying cost in an organization, the higher of the three factors viz., interest, cost of capital or opportunity cost should, be taken into consideration. This may be roughly 20% per annum.

(b) Obsolescence and depreciation : The costs because of obsolescence and depreciation, are very important even though they are very difficult to assess. This factor is relatively higher for spare parts inventory as against raw material inventory. Larger the stock we keep more the risk of obsolescence and as such, the costs are expressed as the percentage costs to the average inventory holding and can be between 2 to 5%.

(c) The cost of storage, handling and stock verification : There are additional costs because of the clerical work involved in handling of materials in the ward, in stock verification, in preservation of materials as well as the costs because of various equipments and facilities created for the purpose of materials. A part of this cost is of a fixed nature. The major portion of the cost including the cost of staff, however, can be treated as variable costs at least in the long run. This cost can be roughly 3 to 5% of the inventory holding.

(d) Insurance Costs : Materials in stocks are either insured against theft, fire etc., or we may have to employ watch & ward organization and also fire fighting organizations. Cost of this may also be 1 to 2%. The average inventory carrying costs can, therefore, be as follows: Interest/costs of capital/opportunity cost 15 to 25% Obsolescence and depreciation cost 2 to 5% Storage, handling etc. 3 to 5% Insurance costs 1 to 2% Total 21 to 37%

 In the Indian Railways, the reasonable assessment of inventory carrying costs shall be about 20 to 25% per year of the average inventory holding. It is again clarified here that these costs are not normally reflected in our accounting system and as such are required to be established by individual Railway.

13.2.3 Shortage Or Stock Out Costs : Whenever an item is out of stock and as such cannot be supplied, it means that some work or the other is delayed and this, in turn, leads to financial loss associated with such stoppage or delay of work.

o For example, if a locomotive remains idle for want of spare parts, the earning capacity of the locomotive is lost for the duration of this period. On the other hand, the spare parts required will have to be purchased on emergency basis or have to be specially manufactured resulting in additional costs.
o Stock out costs can vary from item to item and from situation to situation depending upon the emergency action possible. No attempt therefore, is normally made to evaluate a stock out cost of an item. Nevertheless, it is important to understand the concept of stock out costs, even though the actual quantification is not possible. We should have a rough grading of the items depending upon the possible stock out costs.

13.2.4 Systems Costs : These are the costs which are associated with the nature of the control systems selected. If a very sophisticated model of the relationship between stockout costs, inventory holding cost and cost of ordering is used and operated with the help of a computer, it may give the theoretical minimum of the other costs but the cost of such control system may be sufficiently high to offset the advantages achieved.
  • In most of the situations, however, there is no substantial increase in costs because of the proposed control system and in such cases, these costs can be overlooked.
13.3.0 Inventory Management - Constrains & Problems : Problems of inventory management vary from organization to organization depending upon various variables, some of them are as under:

(a) Whether the demand for the goods is one time (static) or of repetitive nature (dynamic). In Railways, all the non-stock items are treated of static nature and stock items of dynamic nature.

(b) In case of demands of dynamic (repetitive) items, whether future requirements can be assessed with certainty or uncertainty or under risk (probability). Also, whether the demand is fixed over a time or is variable.

(c) Whether the material is manufactured in house or is to be purchased through outside suppliers.

(d) Whether the lead time during which material can be arranged is fixed or is variable.

13.4.0 Economic Order Quantity : Depending upon various variables, different inventory models have been developed. Different models take different costs into account. One of the popular model developed for items of repetitive nature (dynamic), future demands for which can be projected with certainty is Economic Order Quantity (EOQ) model.

  • In addition to factors mentioned above, this model assumes that price of the material remains constant with time and also does not vary with order quantity. This model can be developed mathematically by differentiating total cost of inventory (ordering cost + inventory carrying cost) with respect to Quantity. The formula so derived is given below :
Economic Order Quantity (EOQ) = Sq. Rt. { 2xAxCo / (Cu x Ci)
}

Where,

A = Annual Consumption

Quantity

Co = Cost of placing one

order

Ci = Annual inventory

carrying cost represented as

fraction

Cu = Unit Cost (Rate/Unit) of

the material

13.4.1 EOQ model and various other models and systems of recoupments as explained in Chapter 5 are the answers of two basic questions of inventory management

--When to purchase ?

--How much to purchase?

13.5.0 Measuring Efficiency Of Inventory Management :

13.5.1 Efficiency of an inventory management system is generally measured by two measures ;

(a) Service level : This is the percentage of compliance of demands of user. This level is set by the top management who knows that cost of providing 100% service level (i.e. meeting with all demands for materials at all times) is prohibitively high.

o Therefore, it is attempted to attain a service level between 90 to 98% depending upon criticality of the items. In Railways, we try to comply demands of vital and safety items up to 97 to 98%, recoup imprest items and supply all ferrous and non-ferrous raw materials up to 95% and give compliance of all other items between 90 to 95%.

(b) Inventory turnover ratio : This is a measure of average stocks held in stock at a time. This is measured in percentage by the following formula :
                     
                     Average value of stock of all materials held in stock

T/O ratio = ---------------------------------------------------------------------- 

                   Total value of issues made during the year

In Railways, Stores Balances are reflecting in various capital suspense head e.g., Purchase Suspense (7110, 7120, 7130), Sale Suspense (7140), Stock Suspense (7150, 7160).

o As per accounting system for working out inventory turnover ratio, we divide debit balances outstanding in all above suspense heads on 31st March of the year by total issues made from 1st April to 31st March. This ratio is multiplied by 100 to get percentage. In Railways, we try to achieve turnover ratio of about 27%.

(c) As overstock and inactive items are not contributing towards inventory turnover, we should control their balances. In Railways, total balances of inactive stores (items not moved for past 12 months or more) and overstocks should not be more than 5% of total Stores Balances.

13.6.0 Inventory Control : Inventory Control is the art and science of maintaining the stock level of a given group of items, incurring the least total cost, consistent with other relevant targets and objectives set by the management. Generally, this is measured in terms of service level which is measured in terms of percentage of compliance of demands (requisitions for materials) of user departments and Inventory Turnover ratio as explained above.

13.6.1 Inventory Control Techniques : Various techniques employed for controlling stock levels are ;

(a) Selective Management :- In this technique, various items of stores are classified in various classifications depending upon their consumption, value, unit price, criticality for the organization, source of supply, purchasing problems, rate of drawal from stores, seasonality and stores balances on a particular date. Different approaches of control are being followed for different types of items. Two such classifications ABC & VED are described in paragraphs 13.6.2 & 13.6.3.

(b) Management by exception-- In this technique, items with certain exceptions are tackled on different points of time. For example, overstock items, surplus items and inactive items may require more attention.

(c) Designing of recoupments policies -- Recoupments policies are designed in such a manner that average stocks of materials are optimum.

(d) Rationalization :- Techniques of standardization and variety reduction are used to minimize lead time of the material, and reduce unnecessary inventory carrying costs.

(e) Value Analysis :- Functions performed by the materials are analyzed and alternative designs/raw materials are suggested to achieve the same function at minimum cost.

(f) Computerization :- Computer Outputs can be used for scientific forecast of demand to solve many inventory models, providing optimum safety stocks and for controlling funds.

13.6.2 A-B-C Analysis :This analysis is based upon Pareto Principle according to which in many situations, majority of the activity (70 to 80%) is governed by very few (10 to 20) attributes.

 Hence if all the stock items are analyzed in terms of their annual consumption value, major part of total consumption value on a Railway (about 70-80%) is of only few high consumption value items (say 10 to 20%). These items may be classified as A category. 

 15 to 20% of total consumption is represented by another 15 to 20% items which may be classified as B category . 

 Remaining 5 to 10% consumption is represented by a large no. of small consumption value items which may be classified as C category. 

o Actual ABC classification depends upon management decision. In Railways, we have decided that

 All high consumption value items which represent 70% of total issues, will be classified as A category, 

 Items which represent 20% of total issue will be classified as B category . 

 All remaining items will be C category.

o This analysis is done on the computer as explained below:

(a) First of all annual issue values of all the items which were issued from all the depots are added together to find total issues (in rupees) of the Railway;

(b) Then all the items are sorted in descending sequence of their issue value on the entire Railway (i.e. after adding issues of individual depots);

(c) Then we go on counting the items adding issue value of the item to a 'cumulative issue value' counter. When the value in this counter represents 70% of total issue- value worked out in step (a), after reading a particular item, all the items from top to this item are classified as 'A' category items;

(d) The reading of items is further continued when after reading a particular item and adding its issue value to 'cumulative issue value' counter, value in the counter is equal to 90% of total issues, we mark all items from item next to last A category item to this item as B category item;

(e) All remaining items are classified as C category items.
  • For the purpose of Inventory Control, A category items are most important. Therefore, they are closely monitored at highest level at very frequent intervals.
  • In Railways, their stock levels, consumption forecast etc. are monitored at the level of COS/CMM every month. B category items are monitored at the level of CMM/Dy. COS every quarter or every six month.
  • Stock verification
  1. of A category items is carried out every six months; 
  2. for B category items every year and
  3. once in two years for C category items.
o To achieve better inventory turn over ratio, we intend to keep average stocks of 3 months, 6 months and 12 months of A, B and C category items respectively.

13.6.3 V-E-D Classification : A-B-C Classification is on the basis of consumption value of an item and does not give any importance to the criticality of the item and therefore, only A-B-C Classification is not adequate. Classification done on the basis of criticality of the item is known as V-E-D, where the items are classified as Vital, Essential and Desirable.

  • Vital items are those items which are very critical for the operations and do not permit any corrective time i.e. they cannot be procured off the shelf if they are not available.
  • Essential items are comparatively less vital and work without them cannot be managed for few days. All remaining items are known as Desirable items.
13.6.4 A-B-C / V-E-D Matrix : Tackling the items on the basis of their consumption value and also criticality improves the service to the customer as well as we are able to control the inventory.

We can design the stock levels in such a manner that

  • Maximum service is provided for C category vital items
  • While for A category Desirable items service can be minimum desirable . 
  • For remaining items, service levels can be in between these two levels and average stock holdings can be designed accordingly. 
  • Tackling the items on the basis of their consumption value and also criticality improves the service to the customer as well as we are able to control the inventory.


Numbers indicate the focus priority for best results both in terms of service as well as resources required We can design the stock levels in such a manner that maximum service is provided for C category vital items which provide high satisfaction levels at very little cost, while for A category Desirable items service can be minimum desirable as the require largeresources and provide very low satisfaction. For remaining items, service levels can be in between these two levels and average stock holdings can be designed accordingly.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.

Index -

01. INTEGRATED CONCEPT AND OBJECTIVES OF MATERIALS MANAGEMENT (1) 01.02 रेलपथ निरक्षक तथा सहायक मंडल अभियंता के कर्तव्य (1) 02 रेलपथ (1) 02. ORGANIZATION OF MATERIALS MANAGEMENT DEPARTMENT (1) 02.01 90 यूटीएस रेलों के सम्भाल (1) 02.04 रेल तापमान (1) 02.05 रेल जोड (1) 03 स्लीपरो के कार्य (1) 03. CLASSIFICATION/CODIFICATION NOMENCLATURE OF STORES ON INDIAN RAILWAYS (1) 03.01 विभिन्न प्रकार के स्लीपरो की तुलना (1) 03.02 लचीले बंधन (1) 03.03 स्लीपर बिछाना (1) 04. PLANNING OF NON-STOCK ITEMS AND PROCESSING OF REQUISITION (1) 04.01 ट्रैक के लिए बैलास्ट प्रोफाइल (1) 04.02 फार्मेशन (1) 04.03 ब्रिज (पुल) (1) 05 पाइंट्स तथा क्रासिंग - परिचय एवं परिभाषाए (1) 05 PLANNING OF STOCK ITEMS & SYSTEMS OF RECOUPMENT (1) 05.01 विषेश ले आउट (1) 05.02 पृथक्रकरण (आइसोलेशन ) (1) 05.03 तथा क्रासिंग का अनुरक्षण तथा निरक्षण (1) 05.04 पॉइंट्स एवं क्रासिंग की (1) 06 गोलाई का प्ररंभिक ज्ञान (1) 06 PURCHASE POLICY (1) 06.01 वर्को का पुनः संरेखण (1) 07 Purchase Procedure on zonal Railways (1) 08 TENDER EVALUATION AND MISCELLANEOUS POLICY ISSUES IN PURCHASES (1) 08.01 व्यव्स्तिथ ओवरहालिंग (1) 08.02 रेलपथ अनुरक्षण का वार्षिक कार्यक्रम (1) 08.04 गहरी छनाई (1) 08.04.1 रेलपथ का उठाना लोवेरिंग तथा क्रीप (1) 08.05 छोटी वेल्डेड रेल ( एसडब्लूआर ) (1) 08.06 आन ट्रैक मशीन (1) 08.07 छोटी ट्रैक मशीने (1) 08.09 विद्युतीकृत सेक्शन में हाइट गेज (1) 08.11 अंडर ट्रायल सामग्री का रिकॉर्ड (1) 09 गति प्रतिबन्ध और संकेतक (1) 09 Receipt And Inspection of stores (1) 09.01 ठेकेदार की सुरक्षित कार्य प्रणाली (1) 09.03 रेल संरक्षा आयुक्त की स्वीकृति वाले कार्य (1) 10 निरक्षण का उद्देश्य (1) 10 ISSUE AND DISTRIBUTION OF STORES (1) 10.01 राइडिंग गुणवत्ता तथा राइडिंग इंडेक्स (1) 10.03 सिटीआर तथा टीजीआई (1) 10.04 रेलपथ प्रबंधन पध्दति (टीऍमएस ) (1) 11 RETURNED STORES (1) 11.01 स्लीपरो का बिछाना (1) 12 दुर्घटना (1) 12 Scrap Disposal (1) 12.01 ब्रीच (1) 12.02 डाईवर्शन (1) 13 INVENTORY MANAGEMENT (1) 14 लंबी वेल्डित रेल (परिभाषाए) (1) 14.01 एलडब्लूआर / सीडब्लूआरके लिये स्वीकृत स्थान (1) 14.02 एलडब्लूआरकी डीस्ट्रेसिंग (1) 14.03 एलडब्लूआर / सीडब्लूआर का अनुरक्षण (1) 14.04 रेलपथ पर्येवेक्षक - मेट तथा चाबीदार के लिए अनुमत तथा निषिद्ध कार्य (1) 15 - सर्वेक्षण (1) 15 बयाना राशि और जमानत राशि (1) 15.01 SURVEYING (2) 16 रेलवे टेंडर सिस्टम (Railway Tender System) (1) Accidents (2) Active & Passive Earth Pressure (1) Anti corrosive treatment (1) Ballast (2) Bearings in Bridge (1) Blanketing Material (1) Bridges (2) Buckling of track (1) Building Work (1) Cant deficiency & Cant Excess (1) Census (1) Chequered Tiles (1) Chlorination of Water (2) Chlorination Practices (1) Chlorine demand (1) Civil Engineering - Bridges (2) Civil Engineering - P Way (40) Civil Engineering - Works (5) CMS Crossing (1) Completion report (1) Contour & Contour interval (1) Correction Slip (1) CRS Sanction (1) CTR and TGI Value (1) Curing of Concrete (1) curves (2) Deep Screening (2) Design mode (1) Design of concrete mix (2) Destressing (1) Disinfection of water (1) disposal of human waste: (1) Distressed bridges (2) Distressing of LWR (2) distribution System (1) dry density (1) Duties (3) Duties & Responsibilities (9) Duties of Gateman (1) E01.02 Duties of Keyman / Mate / PWS (1) E02.01 Permanent Way (1) E02.02 Handling of 90 UTS rails (1) E02.05 Rail Temperature (1) E02.06 Rail Joints (1) E02.07 Maintenance of Rail Joints (1) E03.01 SLEEPERS AND FASTENINGS - Functions of Sleepers (1) E03.02 Comparison between Various Types of Sleepers (1) E03.04 Laying of Sleepers (1) E04.02 Ballast Profile for L.W.R. track (1) E04.04 Bridges (1) E05.01 Points & Crossings: Introduction & Definitions (1) E05.04 Maintenance and Inspection of Points and Crossing (1) E05.05 Reconditioning of Points and Crossing (1) E06.01 Basics of Curves (1) E06.02 Realignment of Curve (1) E08.01 MAINTENANCE OF TRACK-Through packing (1) E08.02 Systematic Overhauling (1) E08.03 Annual Programme for Regular Track Maintenances (1) E08.04 Lifting/ Lowering of Track and Creep (1) E08.05 Deep Screening (1) E08.06 Short Welded Rail (1) E08.07 Maintenance of SWR (1) E08.10 Level Crossing (1) E08.11 Equipments at Level Crossing (1) E08.12 Maintenance / Examination / Inspection of Level Crossing / Gate (1) E08.14 Welding of Rails (1) E08.15 Records of Material under Trial (As per Cs.no 99) (1) E09.01 Speed Restriction and Indicators (1) E09.02 Safe Working of Contractors (As per Cs.No 95) (1) E09.03 Works Requiring CRS Sanction (1) E10.01 INSPECTION OF TRACK - Object of Inspection (1) E10.02 Riding Quality and Riding Index (1) E10.03 Track Recording and Oscillograph Car (1) E10.04 CTR and TGI Value (1) E12.01 ACCIDENTS AND BREACHES - Accidents (1) E12.02 Breaches (1) E12.03 Diversion (1) E14.01 LONG WELDED RAIL - Definitions (1) E14.02 Permitted locations for LWR/CWR (1) E14.04 Maintenance of LWR / CWR (1) E14.05 DOs and Don’ts OF LWR For PWM / MATES & KEYMAN (1) Egineering (1) Elastic Fastening (1) Elastic Rail Clip (1) Encroachments of Railway land. (2) Engineering (26) Engineering - Book (3) Examination of Rails (2) Fabrication of Glued joint IN SITU. (1) Flushing cisterns (1) FOB (1) Gateman (2) Greasing of ERCs (1) Grow More Food Scheme (1) Guideline (3) H02 भण्डार विभाग का महत्व (1) H03 भण्डार डिपो की संरचना (1) H04 भण्डार का वर्गीकरण (1) H05 कोडिफीकेशन (1) H06 मानकीकरण एवं उसकी उपयोगिता (1) H07 वित्तीय औचित्य के सिध्दांत (1) H08 क्रय के विभिन्न माध्यम (1) H09 क्रय में विविध अधिमान्यताए (1) H10 भण्डार विभाग के अधिकारियो की क्रय शक्तियां (1) H12 निविदा समिति (1) H13 अनुबंध (1) H16 स्थानीय खरीद (1) H17 भण्डार डिपो में भण्डार प्राप्ति के स्त्रोत (1) H18 महत्वपूर्ण वस्तुए एवं उनकी खरीद (1) H19 भण्डार डिपो का संगठन एवं कार्य (1) H20 प्राप्ति अनुभाग की क्रिया - विधि (1) H21 वार्ड की क्रिया - विधि (1) H22 प्रेषण अनुभाग की क्रिया - विधि (1) H23 बहीखाता अनुभाग की क्रिया - विधि (1) H24 डिपो प्रणाली (1) H25 भण्डार का निरीक्षण (1) H26 अस्वीकृत भण्डार (1) H27 लौटाया गया भण्डार (1) H28 अग्रदाय भण्डार (1) H29 अधिशेष भण्डार (1) H30 रेल सामग्री की बिक्री (1) H31 रद्दी माल और नीलामी बिक्रिया (1) H32 वस्तु - सूची नियंत्रण (1) H33 स्टॉक सत्यापन (1) H34 मांगकरताओ व्दारा डिपुओ से भण्डार प्राप्त करने की प्रक्रिया (1) H35 संक्षिप्त टिप्पणीयां (1) Handling of 90 UTS Rails (1) Height Gauges on Electrified Section (1) Honey combing of concrete & its prevention (1) Hot Weather Patrolling (1) Imprest Store (1) INDEX (2) Indicator Boards & Signages (1) Inspection (6) Insulated joints (1) Isolation (1) Keyman / Mate / PWS (3) Laying of Sleepers (1) LDCE Exam (3) Level Crossing (2) Level crossings (2) Licensing Railway Land cultivation (1) Liner Biting (1) LWR (6) Maintenance (2) Maintenance in Electrified Area (2) Maintenance of CMS Xing (1) Maintenance of P Way (5) Maintenance of Rail Joints (1) Maintenancee of SWR (1) Manson precaution (1) Monsoon Patrolling (2) Numerical rating system (NRS) (1) Optimum moisture content (1) P Way (23) Pandrol Clip (1) pass (1) Patrolling of Rail Permanent Way (6) Permanent Way (2) Permanent Way (P Way) (10) Pile Foundation (1) Points and Crossing (3) Protection of Rail (1) Pumping Water Level (1) PWI (1) PWI / AEN / DEN (1) quality control (2) Question & Answer (62) Rail Clusters (1) Rail Formation (2) rail fracture (1) Rail Joints (1) Rail Renewal (3) Rail Welding (3) Rails Defects (2) Railway Affecting Works (1) Railway Construction (1) Railway Organisation (2) Realignments of Curve) (1) Reconditioning of Points and Crossing (1) Rehabilitation of Bridges (1) Renewal of Rail (1) River Training protection work (1) safe speed (1) Safe Working (1) Safety at P. Way Work Site (1) Schedule of Inspection of Bridges (1) Short Note - Bridge (8) Short Note - P Way (48) Short Note - Works (35) Short Notes - Mislanious (7) Sleeper (4) Sleeper Cribs (1) Soil Consistency (1) Special Layouts (2) Speed Restriction and Indicators (2) Static Water Level (1) Steel Structures (1) Stock sheet (1) Store (34) super elevation (1) Tender System (1) Testing of Rails (2) TGI and OMS (1) Thermit Welding (1) Through Parking (2) Tiles (2) Track Circuited Areas (2) Track Inspection (1) Track Machines (6) Track Management System (1) Track Tolerances (2) track-Overhauling (1) Transitions (1) Turnout (1) urinals (1) USFD (2) Venerable location (1) VIDEO (2) wash basin. (1) Washable Aprons (1) Water Cement ratio (1) Water closetsu (1) Water Quality (1) Water Supply (1) Waterproofing (1) weld failure (1) Well Foundation (1) Winter Precautions (1) Workability of Concrete (1) Working of Contractors (2) works (9) कार्य एवं उद्देश्य (1) ट्रैक रिकॉर्डिंग तथा दोलन लेखी कार (1) रेल पथ मेट के कर्तव्य (1)