Rajbhasha Smart Search



Sort :
Loading...
Go to Page :

Lifting, Lowering of Track and Creep

Lifting Of Track –

1. Lifting of track will become necessary during regarding and for elimination of minor sags, which develop through improper maintenance or yielding soil, to keep a good top.

2. Correct level pegs should be fixed at suitable intervals, before lifting is commenced.

3. Heavy lifting should always be carried out under suitable speed restriction and under the protection of corresponding engineering signals. Lifting should not exceed 75 mm. at a time so as to allow proper consolidation. The easement gradient for the passage of trains should not be steeper than 25 mm. in one rail length of 13 meters. The operation should be repeated until the required level is attained when the track should be finally ballasted, through packed and boxed, the cess being made up to proper level.

4. Lifting should commence from the down hill end carried out in the direction of
rising grade in case of single line. It should proceed in the opposite direction to traffic, in case of double line, care being taken not to exceed the easement grade.

5. While lifting track under bridges and overhead structures and in tunnels it should be ensured that there is no infringement of standard dimensions.

6. In case of curves, it is usual to set the inner rail to the correct level and grade and to raise the outer rail to give the required superelevation, care being taken to see that the cant gradient is within the permissible limit.
Lowering of Track –

1. Lowering of the track should not be resorted to except where it can not be avoided and if resorted to, it should be done under suitable speed restriction and under the protection of Engineering signals.

2. When lowering is to be done, trenches should be made across the track at every 30 M. to the final level in order to give a continuous indication, while the work is in progress. The ballast should be removed sufficiently far away from the track to prevent it getting mixed up with excavated material.

3. The procedure is to clear the spaces between the sleepers, then slightly lift the
track, break the packing beneath and level it into the space between sleepers. This material is then removed and the operation repeated until the final level is
reached. The road should then be ballasted, through packed and boxed, the cess
being cut down to proper level.

4. Lowering as in the case of lifting, should be restricted to a maximum of 75 mm. at a time and the grade for passage of trains should not exceed 25 mm. in a rail length of 13 M. As opposed to lifting, lowering should be carried out in the
direction of the falling grade

5. Work of lifting or lowering of track should be carried out in the presence of
Permanent Way Inspector.

Creep:-

Counteraction and Adjustment of creep –

(1) General.-Rails have a tendency to move gradually in the direction of the dominant traffic. It is believed to be caused by the ‘ ironing out ’ of yielding track by the moving load, augmented by braking loads, and by the impact of the wheels on the running-on ends of the rails, particularly at times when they are in a state of expansion or contraction. Among the troubles caused by ‘creep’ are –

(a) Sleepers getting out of square.
(b) Distortion of gauge.
(c) Loosening of joints.
(d) Shearing and breaking of spikes, bolts and fish-plates.
(e) Buckling in extreme cases.

(2) Causes for creep in Track –

The following are some of the avoidable causes to which creep is attributed :

(a) Inadequate toe loads of the rail to sleeper fastening and rails not secured properly to sleeper.
(b) Inadequate ballast resistance to the movement of sleepers due to poor or insufficient ballast or other causes.

(c) Inefficient or badly maintained rail joints.
(d) Rails too light for the traffic they carry.
(e) Improper expansion gaps.
(f) Decaying sleepers, uneven spacing of sleepers.
(g) Lack of proper drainage.
(h) Yielding formation resulting in uneven cross levels.
(i) Loose/uneven packing.
(j) Rail seat wear in metal sleeper road.

(3) Precautions to reduce creep –

(a) For reducing creep, it must be ensured that the rails are held firmly to the sleepers and adequate ballast resistance is available. All spikes, screws and keys should be driven home, the sleepers properly packed and crib and shoulder ballast should be compacted. Rail anchors should be provided wherever necessary.

(b) With steel trough and cast iron plate sleepers and in the case of sleepers where elastic fastenings and other fastenings with adequate toe load are used, no trouble is normally experienced. Careful watch should be kept for a series of jammed joints. Not more than six jammed joints continuously should be permitted in the case of single rails. In case of SWR not more than two consecutive jammed joints should be permitted at rail temperatures lower than “tm” in the case of Zone I and II and “tm-5” in the case of Zone III and IV. On girder bridges adjustment may be necessary at regular intervals. Anti-creep devices should be provided on the  approaches of girder bridges for adequate length.

(c) : The PSC sleepers with elastic fastenings are considered as creep resistant and therefore no other creep anchors are required. In case, excessive creep is observed on PSC sleeper road, the condition of elastic fastenings, sleepers and adequacy of ballast resistance should be examined. Action for replacement/renewal of fittings, sleepers and providing adequate ballast resistance etc. should be taken as necessary.

(4) Creep Register –

Creep registers should be maintained in the pro forma. Entries should be complete as regards kilometerage, section and length of rail, sleeper density, type and number of anchors per rail length used. Periodical readings of creep should be recorded in the prescribed pro forma. Separate page should be allotted for each km. Frequency of recording of creep should be specified by the Divisional Engineer taking into consideration the rate of creep. The Assistant Engineer should test checks the register frequently, particularly sections which are prone to creep.

(5) Creep indication Posts –

 Creep indication posts square to the track should be erected on either side of the track on the cess at intervals of about one km. These may be un serviceable rail posts with chisel mark square to the joints . The top of the post should be about 25 mm. above the rail level and the amount of creep one way or the other measured with a fishing cord stretched over the chisel marks.

(6) Permissible amount of creep – Creep in excess of 150 mm. shall not be permitted.

(7) Adjustment of creep – Adjustments of creep should be carried out in the following manner:

(a) Careful measurement of expansion gaps, as existing, should be done and appropriate length which can be dealt with in one operation should be chosen. The total amount of gap in the length should be equal to the standard expansion gap required for the temperature at the time, multiplied by the number of joints in
the length.

(b)Work should start at the running-on end of the length, commonly just beyond the points and crossings or level crossings. The work of creep adjustments should be carried out under the protection of engineering signals by the Permanent Way Inspector as envisaged. Before pulling back is commenced the keys are knocked out and fish-plates removed or eased. Correct expansion liners should be used and the rails should be pulled back with bars. If the fish-plates are removed, the bars can pull against a tommy bar thrust through a bolt hole. Next, the rail is keyed up, the bolts of joints correctly tightened up, and the expansion liner moved to the next joint, whereupon the process is repeated.

(c) It is a good practice to adjust creep before the commencement of summer. It is desirable to pull back the rails during the cool hours of the day.

(d) Mechanical and hydraulic devices are available for adjustment of creep. Such a device can be set with the wide joints behind it and the tight joints ahead of it. Expansion liners are put in all the wide joints. All keys, spikes and fish bolts are loosened. The adjuster then closes up the rails behind it by pushing, leaving a gap of some centimeters between the rail ends opposite the machine. The corrected rails are then fastened up.

(e) The machine is next attached to the rail ahead of it, keys, spikes and fish bolts
loosened for that rail and those beyond it. These rails are then pulled until only the normal expansion gap is left opposite the machine. The operation leaves some of the gaps wide and it is then necessary to fix the machines further ahead in order to close them upto normal by pulling against expansion liners.

(f) When the value of total gap existing is more than the standard expansion gap required for the temperature at the time of adjustment multiplied by the number of joints, it is necessary to provide closure rails. When closure rails are put in, a speed restriction of 30 km/h should be imposed, which should be removed, when
closure rail is changed.

(g) During adjustment of creep, the sleeper spacing should be adjusted, if necessary, special attention being given to the joint and shoulder sleeper spacing. (8) Provision of Anchors to arrest Creep –To arrest excessive creep on wooden sleepered road, not provided with anti-creep fastenings, adequate number of anchors of approved design should be provided; no anchors being provided at the
joint sleepers. Both rail seats of the sleepers should be anchored on the same side. In addition to sufficient directional anchors is being provided, back up anchors may be provided if considered necessary.

(9) Prevention of creep on metal sleeper road–

 Creep on cast iron plate sleepers should be counteracted as follows:

(a) On C.I. plate sleepers all keys should be driven in the direction of traffic on the double line and alternately in the opposite direction on single line.

(b) On steel trough road normally keys are driven as indicated. However, where heavy creep is experienced on double line, all the four keys may be driven in the direction of the creep (generally in the direction of traffic). On single line keys may be driven in the opposite direction on alternate sleepers

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.

Index -

Question & Answer (63) Short Note - P Way (48) Civil Engineering - P Way (43) Short Note - Works (35) Store (34) Engineering (26) P Way (23) Permanent Way (P Way) (13) Duties & Responsibilities (9) Track Machines (9) works (9) Short Note - Bridge (8) Short Notes - Miscellaneous (7) Inspection (6) LWR (6) Patrolling of Rail Permanent Way (6) Civil Engineering - Works (5) Engineering - Book (5) Maintenance of P Way (5) Sleeper (4) Duties (3) Guideline (3) Handbook (3) Keyman / Mate / PWS (3) LDCE Exam (3) Points and Crossing (3) Rail Renewal (3) Rail Welding (3) 15.01 SURVEYING (2) Accidents (2) Ballast (2) Bridges (2) Chlorination of Water (2) Civil Engineering - Bridges (2) Deep Screening (2) Design of concrete mix (2) Distressed bridges (2) Distressing of LWR (2) Encroachments of Railway land. (2) Examination of Rails (2) Gateman (2) INDEX (2) Level Crossing (2) Level crossings (2) Maintenance (2) Maintenance in Electrified Area (2) Monsoon Patrolling (2) Permanent Way (2) Rail Formation (2) Rails Defects (2) Railway Organisation (2) Special Layouts (2) Speed Restriction and Indicators (2) Testing of Rails (2) Through Parking (2) Tiles (2) Track Circuited Areas (2) Track Tolerances (2) USFD (2) VIDEO (2) Working of Contractors (2) curves (2) quality control (2) 01. INTEGRATED CONCEPT AND OBJECTIVES OF MATERIALS MANAGEMENT (1) 01.02 रेलपथ निरक्षक तथा सहायक मंडल अभियंता के कर्तव्य (1) 02 रेलपथ (1) 02. ORGANIZATION OF MATERIALS MANAGEMENT DEPARTMENT (1) 02.01 90 यूटीएस रेलों के सम्भाल (1) 02.04 रेल तापमान (1) 02.05 रेल जोड (1) 03 स्लीपरो के कार्य (1) 03. CLASSIFICATION/CODIFICATION NOMENCLATURE OF STORES ON INDIAN RAILWAYS (1) 03.01 विभिन्न प्रकार के स्लीपरो की तुलना (1) 03.02 लचीले बंधन (1) 03.03 स्लीपर बिछाना (1) 04. PLANNING OF NON-STOCK ITEMS AND PROCESSING OF REQUISITION (1) 04.01 ट्रैक के लिए बैलास्ट प्रोफाइल (1) 04.02 फार्मेशन (1) 04.03 ब्रिज (पुल) (1) 05 पाइंट्स तथा क्रासिंग - परिचय एवं परिभाषाए (1) 05 PLANNING OF STOCK ITEMS & SYSTEMS OF RECOUPMENT (1) 05.01 विषेश ले आउट (1) 05.02 पृथक्रकरण (आइसोलेशन ) (1) 05.03 तथा क्रासिंग का अनुरक्षण तथा निरक्षण (1) 05.04 पॉइंट्स एवं क्रासिंग की (1) 06 गोलाई का प्ररंभिक ज्ञान (1) 06 PURCHASE POLICY (1) 06.01 वर्को का पुनः संरेखण (1) 07 Purchase Procedure on zonal Railways (1) 08 TENDER EVALUATION AND MISCELLANEOUS POLICY ISSUES IN PURCHASES (1) 08.01 व्यव्स्तिथ ओवरहालिंग (1) 08.02 रेलपथ अनुरक्षण का वार्षिक कार्यक्रम (1) 08.04 गहरी छनाई (1) 08.04.1 रेलपथ का उठाना लोवेरिंग तथा क्रीप (1) 08.05 छोटी वेल्डेड रेल ( एसडब्लूआर ) (1) 08.06 आन ट्रैक मशीन (1) 08.07 छोटी ट्रैक मशीने (1) 08.09 विद्युतीकृत सेक्शन में हाइट गेज (1) 08.11 अंडर ट्रायल सामग्री का रिकॉर्ड (1) 09 गति प्रतिबन्ध और संकेतक (1) 09 Receipt And Inspection of stores (1) 09.01 ठेकेदार की सुरक्षित कार्य प्रणाली (1) 09.03 रेल संरक्षा आयुक्त की स्वीकृति वाले कार्य (1) 10 निरक्षण का उद्देश्य (1) 10 ISSUE AND DISTRIBUTION OF STORES (1) 10.01 राइडिंग गुणवत्ता तथा राइडिंग इंडेक्स (1) 10.03 सिटीआर तथा टीजीआई (1) 10.04 रेलपथ प्रबंधन पध्दति (टीऍमएस ) (1) 11 RETURNED STORES (1) 11.01 स्लीपरो का बिछाना (1) 12 दुर्घटना (1) 12 Scrap Disposal (1) 12.01 ब्रीच (1) 12.02 डाईवर्शन (1) 13 INVENTORY MANAGEMENT (1) 14 लंबी वेल्डित रेल (परिभाषाए) (1) 14.01 एलडब्लूआर / सीडब्लूआरके लिये स्वीकृत स्थान (1) 14.02 एलडब्लूआरकी डीस्ट्रेसिंग (1) 14.03 एलडब्लूआर / सीडब्लूआर का अनुरक्षण (1) 14.04 रेलपथ पर्येवेक्षक - मेट तथा चाबीदार के लिए अनुमत तथा निषिद्ध कार्य (1) 15 - सर्वेक्षण (1) 15 बयाना राशि और जमानत राशि (1) 16 रेलवे टेंडर सिस्टम (Railway Tender System) (1) Active & Passive Earth Pressure (1) Anti corrosive treatment (1) Bearings in Bridge (1) Blanketing Material (1) Buckling of track (1) Building Work (1) CMS Crossing (1) CRS Sanction (1) CTR and TGI Value (1) Cant deficiency & Cant Excess (1) Census (1) Chequered Tiles (1) Chlorination Practices (1) Chlorine demand (1) Completion report (1) Contour & Contour interval (1) Correction Slip (1) Curing of Concrete (1) Design mode (1) Destressing (1) Disinfection of water (1) Duties of Gateman (1) E01.02 Duties of Keyman / Mate / PWS (1) E02.01 Permanent Way (1) E02.02 Handling of 90 UTS rails (1) E02.05 Rail Temperature (1) E02.06 Rail Joints (1) E02.07 Maintenance of Rail Joints (1) E03.01 SLEEPERS AND FASTENINGS - Functions of Sleepers (1) E03.02 Comparison between Various Types of Sleepers (1) E03.04 Laying of Sleepers (1) E04.02 Ballast Profile for L.W.R. track (1) E04.04 Bridges (1) E05.01 Points & Crossings: Introduction & Definitions (1) E05.04 Maintenance and Inspection of Points and Crossing (1) E05.05 Reconditioning of Points and Crossing (1) E06.01 Basics of Curves (1) E06.02 Realignment of Curve (1) E08.01 MAINTENANCE OF TRACK-Through packing (1) E08.02 Systematic Overhauling (1) E08.03 Annual Programme for Regular Track Maintenances (1) E08.04 Lifting/ Lowering of Track and Creep (1) E08.05 Deep Screening (1) E08.06 Short Welded Rail (1) E08.07 Maintenance of SWR (1) E08.10 Level Crossing (1) E08.11 Equipments at Level Crossing (1) E08.12 Maintenance / Examination / Inspection of Level Crossing / Gate (1) E08.14 Welding of Rails (1) E08.15 Records of Material under Trial (As per Cs.no 99) (1) E09.01 Speed Restriction and Indicators (1) E09.02 Safe Working of Contractors (As per Cs.No 95) (1) E09.03 Works Requiring CRS Sanction (1) E10.01 INSPECTION OF TRACK - Object of Inspection (1) E10.02 Riding Quality and Riding Index (1) E10.03 Track Recording and Oscillograph Car (1) E10.04 CTR and TGI Value (1) E12.01 ACCIDENTS AND BREACHES - Accidents (1) E12.02 Breaches (1) E12.03 Diversion (1) E14.01 LONG WELDED RAIL - Definitions (1) E14.02 Permitted locations for LWR/CWR (1) E14.04 Maintenance of LWR / CWR (1) E14.05 DOs and Don’ts OF LWR For PWM / MATES & KEYMAN (1) Egineering (1) Elastic Fastening (1) Elastic Rail Clip (1) FOB (1) Fabrication of Glued joint IN SITU. (1) Flushing cisterns (1) Greasing of ERCs (1) Grow More Food Scheme (1) H02 भण्डार विभाग का महत्व (1) H03 भण्डार डिपो की संरचना (1) H04 भण्डार का वर्गीकरण (1) H05 कोडिफीकेशन (1) H06 मानकीकरण एवं उसकी उपयोगिता (1) H07 वित्तीय औचित्य के सिध्दांत (1) H08 क्रय के विभिन्न माध्यम (1) H09 क्रय में विविध अधिमान्यताए (1) H10 भण्डार विभाग के अधिकारियो की क्रय शक्तियां (1) H12 निविदा समिति (1) H13 अनुबंध (1) H16 स्थानीय खरीद (1) H17 भण्डार डिपो में भण्डार प्राप्ति के स्त्रोत (1) H18 महत्वपूर्ण वस्तुए एवं उनकी खरीद (1) H19 भण्डार डिपो का संगठन एवं कार्य (1) H20 प्राप्ति अनुभाग की क्रिया - विधि (1) H21 वार्ड की क्रिया - विधि (1) H22 प्रेषण अनुभाग की क्रिया - विधि (1) H23 बहीखाता अनुभाग की क्रिया - विधि (1) H24 डिपो प्रणाली (1) H25 भण्डार का निरीक्षण (1) H26 अस्वीकृत भण्डार (1) H27 लौटाया गया भण्डार (1) H28 अग्रदाय भण्डार (1) H29 अधिशेष भण्डार (1) H30 रेल सामग्री की बिक्री (1) H31 रद्दी माल और नीलामी बिक्रिया (1) H32 वस्तु - सूची नियंत्रण (1) H33 स्टॉक सत्यापन (1) H34 मांगकरताओ व्दारा डिपुओ से भण्डार प्राप्त करने की प्रक्रिया (1) H35 संक्षिप्त टिप्पणीयां (1) Handling of 90 UTS Rails (1) Height Gauges on Electrified Section (1) Honey combing of concrete & its prevention (1) Hot Weather Patrolling (1) Imprest Store (1) Indicator Boards & Signages (1) Insulated joints (1) Isolation (1) Laying of Sleepers (1) Licensing Railway Land cultivation (1) Liner Biting (1) Maintenance of CMS Xing (1) Maintenance of Rail Joints (1) Maintenancee of SWR (1) Manson precaution (1) Numerical rating system (NRS) (1) Optimum moisture content (1) PWI (1) PWI / AEN / DEN (1) Pandrol Clip (1) Pile Foundation (1) Protection of Rail (1) Pumping Water Level (1) Rail Clusters (1) Rail Joints (1) Railway Affecting Works (1) Railway Construction (1) Realignments of Curve) (1) Reconditioning of Points and Crossing (1) Rehabilitation of Bridges (1) Renewal of Rail (1) River Training protection work (1) Safe Working (1) Safety at P. Way Work Site (1) Schedule of Inspection of Bridges (1) Sleeper Cribs (1) Soil Consistency (1) Static Water Level (1) Steel Structures (1) Stock sheet (1) TGI and OMS (1) Tender System (1) Thermit Welding (1) Track Inspection (1) Track Maintenance (1) Track Management System (1) Transitions (1) Turnout (1) Venerable location (1) Washable Aprons (1) Water Cement ratio (1) Water Quality (1) Water Supply (1) Water closetsu (1) Waterproofing (1) Well Foundation (1) Winter Precautions (1) Workability of Concrete (1) disposal of human waste: (1) distribution System (1) dry density (1) pass (1) rail fracture (1) safe speed (1) super elevation (1) track-Overhauling (1) urinals (1) wash basin. (1) weld failure (1) कार्य एवं उद्देश्य (1) ट्रैक रिकॉर्डिंग तथा दोलन लेखी कार (1) रेल पथ मेट के कर्तव्य (1)