1.Track Structure for private siding with operating speed of 80  to 100 kmph is same as the track structure as specified for

a)  Group B route

b) Group A route

c) Group D route* 

d)Group C route

Answer - c) Group D route

2. Track structure for private siding with operating speed 50 to 80 kmph is the same as track structure as specified for 

a)Group A route

b) Group B route

c) Group D route 

d)Group E route*

Answer -d)Group E route*

3. Indicate which of the statement is incorrect with regard to coning of Wheels 

a)coning of wheels help the vehicle to negotiate a curve smoothly

b) It helps in smooth riding 

c) It increases wear and Tear of wheel flanges* 

d)it enables the outer wheel of vehicle to take a longer distance

e) it restricts the swaying of vehicles

Answer - c) It increases wear and Tear of wheel flanges* 

4. Tilting of rails is done at a slope of

a.1 in 30 

b.1 in 25  

c.1 in 20*

d.1 in 15

Answer -c.1 in 20*

5. Clear perpendicular distance between inner faces of two rails is

a.Gauge of track* 

b.Inner gauge

c.Wheel base

d.Wheel gauge

Answer -a.Gauge of track* 

6. The ratio of wheel diameter to gauge is about

a.0. 40  b.0.55

 c.0. 75* 

d.0. 90

Answer - c.0. 75* 

7. The train runs faster on BG than on MG rail because its speed is directly proportional to 

a) Weight of the train* 

b) Gauge width  

c)Policy of Railway Board

d) Length of the train 

Answer - a) Weight of the train* 

8. The ratio of maximum cant   e and gauge G in India is about   

a)1 / 100 

b) 1 / 50

c)1 /10* 

d) 1 / 25 

Answer -c)1 /10* 

9. “Composite sleeper index” is employed to determine

a) sleeper density requirement

b) number of fixtures required for a particular type of sleeper

c) durability of sleeper

d) mechanical strength of wooden sleepers and thereby gives its suitability as to be used as li sleepers.*

Answer - d) mechanical strength of wooden sleepers and thereby gives its suitability as to be used as li sleepers.*

10. The maximum permissible speed recommended for Indian Railways for 1 in 8 and half crossing is 

a)16 kmph* 

b) 20 kmph  

c)24 kmph

d) 32 kmph 

Answer -a)16 kmph* 

11.What is the weight per meter length of 52 kg Rail?

a.54.14 kg 

b.50.25 kg 

c.51.89 kg* 

d.53.85 kg 

Answer -c.51.89 kg* 

12.What is the height of 60 kg rail section?

a.180 mm

b.172 mm*

c.185 mm

d.165 mm

Answer -b.172 mm*

13.In M+7 sleeper density, how many sleepers are there in a km  Track

.a.1660 nos

b.1540 nos.*

 c.1310 nos. 

d.1440 nos. 

Answer -b.1540 nos.*

14.What is the assessed GMT service life of 60 kg 90 UTS rail?

a.650 GMT

b.600 GMT

c.800 GMT*

d.500 GMT

Answer -c.800 GMT*

15.What is the assessed GMT service life of 52 kg 90 UTS rail. 

a.650 GMT

b.600 GMT

c.525 GMT*

d.500 GMT

Answer - c.525 GMT*

16.What is the full form UTS of rails

a.Ultimate technical Strength

b.Ultimate tensile Strength*

c.Upper Top surface

d.None of above

Answer -b.Ultimate tensile Strength*

17.What is the width of Head of 52 kg Rail section 

a.70 mm

b.75 mm

c.67 mm*

d.60 mm

Answer - c.67 mm*

18.What is the full form of GMT

a.Gross Million Tonnes*

b.Gross minimum thickness

c.Gross Maximum thickness

d.None of above

Answer -a.Gross Million Tonnes*

19.In Indian Railway how many Gauges of Track has been adopted

a.1 

b.3* 

c.2 d. 

Answer -b.3* 

20.What is the Highest speed of train in Indian Railway

a.140 KMPH

b.120 kmph 

c.160 kmph* 

d.130 kmph 

Answer -c.160 kmph* 

21.How many divisions in Northern Railway

a.5* 

b.4 

c.6 

d.3 

Answer -a.5* 

22.What do you mean by BG

a.Big Gauge

b.Broad Gauge*

c.Buffer gauge

d.None of above

Answer -b.Broad Gauge*

23.What do you mean by RDSO

a.Research & Development Standard organisation*

b.Railway  Development & Standard organisation

c.Regional  Development  &   Standard organisation 

d.None of above

Answer - a.Research & Development Standard organisation*

24.Where is the Head Quarter of Northern Railway 

a.New Delhi*

b.Lucknow

c.Mumbai

d.Calcutta

Answer - a.New Delhi*

25.What is the highest post in Railway

a.General Manager

b.Chief Engineer

c.Chairman Railway Board* 

d.Divisional Railway Manager

Answer -c.Chairman Railway Board* 

26.What is the standard distance between lines in Broad Gauge

a.1670 mm

b.1676 mm*

c.1665 mm

d. 1680 mm

Answer -b.1676 mm*

27.What do you mean by LWR

a.Long welded Rail*

b.Long weld able Rail

c.Linear welded raild.None of above.

Answer -a.Long welded Rail*

28.On the basis of temperature how many zones are in Indian railway  

a.2 

b.6 

c.4* 

d.7 

Answer -c.4* 

29.What is the minimum distance centre to centre of straight tracks for new works/alterations to existing  works.   

a. 4265 mm.  

b.3660 mm.  

 c.5300 mm.*  

d 4365 mm. 

Answer - c.5300 mm.*  

30.What is the full form of OMS used for track recording 

a.Outer most Surface

b.Oscillation Monitoring system*

c.Only measuring system 

 d.Official measurement system 

Answer - b.Oscillation Monitoring system*

31.What is the frequency of track recording of the sections having speed more than 110 kmph to 130 kmph 

a.4 Months

b.2 Months

c.6 Months

d.3 Months* 

Answer -d.3 Months* 

32.What is the full form of PQRS used for Track renewal works.

a.Plasser quick Relaying system*

b.Please quick return services

c.Poor Quality renewal  system

d.None of above

Answer -a.Plasser quick Relaying system*

33.Minimum radius of curve on Broad gauge

a.175 meter*

b.215 meterc.

c.146 meterd.

d.200 meter

Answer - a.175 meter*

34.Minimum check rail clearance at Level crossing

a.45 mm

b.51 mm*

c.50 mm

d.57 mm

Answer -b.51 mm*

35.Maximum height above rail level of  high passenger Platform 

a.860 mm

b.900 mm

c.840 mm&*

d.875 mm

Answer -c.840 mm&*

36.Minimum clearance between toe of Open switch and stock rail for new works

a.115 mm*

b.120 mm

c.95 mm

d.110 mm

Answer -a.115 mm*

37.What is the formula of TGI for track recording 

a.UI+4TI+6GI+AI/10

b.2UI+TI+GI+6AI/10* 

c.3UI+TI+2GI+5AI/10

d.2UI+2tI+2GI+4AI/103

Answer -b.2UI+TI+GI+6AI/10* 

8.What is the limit of Unevenness of A category of track

a.0 to 10 mm

b.0 to 5 mm

c.0 to 6 mm*

d.0 to 8 mm

Answer -c.0 to 6 mm*

39.What is the difference between rail flange of 60 kg & 52 rail section 

a.20 mm

b.18 mm

c.14 mm*

d.16 mm

Answer -c.14 mm*

40. what is the value of long chord for measuring unevenness in track recording

a.3.6 meter

b.9.6 meter*

c.7.2 meter

d.4.8 meter

Answer -b.9.6 meter*

41.   Frequency of TTM  tamping  on PSC sleepers track

a.2 years or 100 GMT which ever is earlier*

b.2 years or 150 GMT which ever is earlier

c.1.5 years or 200 GMT which ever is earlier

d.2 years or 175 GMT which ever is earlier

Answer -a.2 years or 100 GMT which ever is earlier*

42. How many sleepers are there in Fan shaped 1 in 12 turnout

a.85 sleepers

b.96 sleepers*

c.90 sleepers

d.100 sleepers

Answer -b.96 sleepers*

43.Minimum wing rail clearance opposing nose of crossing on Fan shaped  turnout

a.45 mm

b.40 mm

c.41 mm*

d.44 mm

Answer -c.41 mm*

44.Overall length of fan shaped 1 in 12 Turnout

a.39975 mm*

b.41004 mm

c.28613 mm

d.None of above

Answer - a.39975 mm*

45.What is the full form of TGI

a.Track Geometry Index*

b.Track general Index

c.Track gravity Index

d.None of above

Answer -a.Track Geometry Index*

46.Permissible speed of Turnout with 1 in 12 curved switches

a.40 kmph*

b.25 kmph 

c.15 kmph 

d.20 kmph 

Answer - a.40 kmph*

47.Permissible speed of Turnout with 1 in 8.5 curved switches

a.40 kmph 

b.25 kmph*

c.15 kmph 

d.20 kmph 

Answer -b.25 kmph*

48.How many green flags are with Patroller during Hot weather patrolling.

a.02 

b.03 

c.01 

d.None of above* 

Answer - d.None of above* 

49.Lowest level of staff/supervisor competent for TTM tamping operation in LWR/CWR.

a.Gang Mate

b.PWS

c.PWI*

d.Keyman.

Answer - c.PWI*

50.Lowest level of staff/supervisor competent for Lifting/Lowering of track in LWR/CWR.

a.Keyman.

b.Gangmate.

c.PWI.

d.PWS.* 

Answer -d.PWS.* 

51.Lowest level of staff/supervisor competent for packing or renewal of single isolated sleeper not requiring lifting or slewing of track in LWR/CWR

a.PWI

b.Keyman

c.Gangmate*

d.PWS

Answer -c.Gangmate*

52.Lowest level of staff/supervisor competent of Renewal of fastenings not requiring lifting in LWR/CWR.

a.PWS

b.Gangmate

c.Keyman*

d.Gangman

Answer -c.Keyman*

53.Lowest level of staff/supervisor competent for Renewal/recoupment of fastenings requiring lifting in LWR/CWR.

a.PWS

b.Gangmate*

c.Keyman

d.Gangman

Answer -b.Gangmate*

54.Lowest level of staff/supervisor competent for Screening of ballast other than deep screening in LWR/CWR.

a.PWS

b.Keyman

c.Gangmate*

d.Gangman

Answer - c.Gangmate*

55.Lowest level of staff/supervisor competent for Organising Hot weather patrolling during summer months in LWR/CWR.

a.Gangmate

b.PWI*

c.Keyman

d.PWS

Answer - b.PWI*

31.Lowest level of staff/supervisor competent for all operations regarding distressing in LWR/CWR.

a.PWI*

b.PWS

c.Gangmate

d.Keyman

Answer - a.PWI*

56.Lowest level of staff/supervisor competent for passing of first train after buckling in LWR/CWR.  

a.PWI*

b.PWS

c.Gangmate

d.Keyman

Answer - a.PWI*

57.How many zones are in Indian railway

a.8 

b.10 

c.16* 

d.12 

Answer - c.16* 

58.In LWR What is the range of Destressing temperature in 52 kg and heavier section

a.Mean rail temp+5 0C  to  Mean rail temp+10 0C*

b.Mean rail temp+5 0C  to  Mean rail temp+15 0C   

c.Mean rail temp  to  Mean rail temp+10 0C   

d.Mean rail temp+2 0C  to  Mean rail temp+10 0C 

Answer -a.Mean rail temp+5 0C  to  Mean rail temp+10 0C*

59.What is full form of SPURT car

a.Self propelled ultrasonic rail testing car*

b.Self pulled united rail testing car

c.Self pumped universal testing car

d.None of above

Answer -a.Self propelled ultrasonic rail testing car*

60.What do you mean by 60 kg rail

a.Weight of rail in 1 meter* 

b.Area of rail of 1 meter

c.Weight of rail in 1 feet

d.Volume of rail in 1 meter

Answer - a.Weight of rail in 1 meter* 

61.Points & Crossing is laid at a cant of 

a.1 in 20 

b.1 in 10 

c.1 in 15 

d.NIL*

Answer -  d.NIL*

62.Minimum permissible vertical wear on nose of  a 52 kg CMS crossing on Rajdhani route is 

 i)6mm

ii)8mm*

iii)10mm

iv)12 mm

Answer - ii)8mm*

63.Normal life of detonators is  

e.5 years 

f.10 years

g.7 years *

h.6 years.

Answer - g.7 years *

64.Maximum distance apart of trolley refuges on bridges with main spans of 100metre or more is

 i.50 mtr

j.100 mtr

k.200 mtr

l.a refuge over each pair*

Answer - l.a refuge over each pair*

65.Permissible creep in track is  

m.50 mm

n.100 mm

o.125 mm

p.150 mm.*

Answer -p.150 mm.*

66. Maximum distance covered in a day by  a Patrolman should not normally exceed

q.2 km. 

r.5 km. 

s.10 km. 

t.20 km .*

Answer - t.20 km .*

67.Curve inspection shall be carried out by Sectional PWI

a.Once in three months

b.Once in six months

c.Once in four months*

d.None of above

Answer -c.Once in four months*

68.An accident has taken place at out station and main line is blocked and relief train is to be turned out without medical car.  The hooter shall be:

a.3 long 

b.4 long*

c. 4 long, 1 short

d.3 long, and 1 short

Answer - b.4 long*

69.Minimum speed restriction to be imposed for Track renewal is:- 

 (a)Stop dead & 10 Kmph

(b)10 Kmph 

(c)15 Kmph 

(d)20 Kmph*

Answer - (d)20 Kmph*

70.Service life in terms of total GMT carried for 52 kg. 90 UTS rail is:-

 (a)425 GMT

(b)475 GMT

(c)525 GMT*

(d)545 GMT

Answer - (c)525 GMT*

71.Minimum rail section recommended for section having traffic  more than 20 GMT is

(a)90 UTS

(b)52 Kg.

(c)60 Kg.*

(d)None of the above.

Answer - (c)60 Kg.*

72.Lubrication of ERC and inserts in corrosion prone areas and platform line is done:- 

(a)Once in a month

(b)Once in a fortnight.

(c)Once in a week.

(d)Once in a year.*

Answer - (d)Once in a year.*

73.Vertical wear permissible for 60kg/90UTS. rails is:- 

(a)23 mm. 

(b)10 mm. 

(c)13 mm.*

(d)15 mm. 

Answer - (c)13 mm.*

74.   Permissible wear of web & foot of rail  due to  corrosion  is:-

 (a)15 mm. 

(b)1.5 mm.*

(c)0.5 mm. 

(d)2.5 mm. 

Answer - (b)1.5 mm.*

75.Minimum depth of ballast cushion below the bottom of sleeper at the rail seat on BG group A route should be :- 

(a)350 mm. 

(b)250 mm.

 (c)300 mm.*

(d)325 mm. 

Answer -  (c)300 mm.*

76.Sleeper density for group ‘A’ route with traffic density more than 20 GMT is:- 

(a)1560 sleepers/ Km.

(b)1660 sleepers/ Km.* 

(c)1540 sleepers/ Km.

(d)1340 sleepers/ Km.

Answer - (b)1660 sleepers/ Km.* 

77.Track structure for CC+8 t+ 2 t loaded trains is:- 

(a)52 Kg 90 UTS;PSC 1540 sleepers/ Km.; 250 mm ballast. 

(b)60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*

(c)52 Kg 72 UTS;PSC 1540 sleepers/ Km.; 300 mm ballast. 

(d)90 R;PSC 1340 sleepers/ Km.; 250 mm ballast.

Answer - (b)60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*

78.Deep screening of entire track must be done at least:- 

(a)Once in a quarter.

(b)Once in a year.

(c)Once in 5 years.

(d)Once in 10 years.* 

Answer - (d)Once in 10 years.* 

79.Service life of Glued insulated rail joint of 60 Kg rail is:- 

(a)300 GMT. 

(b)200 GMT.*

(c)400 GMT. 

(d)150 GMT. 

Answer - (b)200 GMT.*

80.Service life of improved SEJ of 60 Kg rail is:-

(a)400 GMT. 

(b)300 GMT. 

(c)200 GMT.*

(d)150 GMT. 

Answer - (c)200 GMT.*

81.Service life of CMS crossing ( 52 Kg rail) is:- 

(a)400 GMT.

(b)300 GMT.

 (c)200 GMT. 

(d)150 GMT.*

Answer - (d)150 GMT.*

82.D&G charges for works estimates of CTR(P) is:- 

(a)2.25%.

 (b)1.8%.*

(c)1.35%. 

(d)1.62%. 

Answer -  (b)1.8%.*

83.  What is speed restriction on deep screening site done by BCM and tamped by machine     followed with  DGS?

(a)20

 (b)30 

(c)40* 

(d)10

Answer -(c)40* 

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.

Disclaimer: The Information/News/Video provided in this Platform has been collected from different sources. We Believe that “Knowledge Is Power” and our aim is to create general awareness among people and make them powerful through easily accessible Information. NOTE: We do not take any responsibility of authenticity of Information/News/Videos.

Index -

01. INTEGRATED CONCEPT AND OBJECTIVES OF MATERIALS MANAGEMENT (1) 01.02 रेलपथ निरक्षक तथा सहायक मंडल अभियंता के कर्तव्य (1) 02 रेलपथ (1) 02. ORGANIZATION OF MATERIALS MANAGEMENT DEPARTMENT (1) 02.01 90 यूटीएस रेलों के सम्भाल (1) 02.04 रेल तापमान (1) 02.05 रेल जोड (1) 03 स्लीपरो के कार्य (1) 03. CLASSIFICATION/CODIFICATION NOMENCLATURE OF STORES ON INDIAN RAILWAYS (1) 03.01 विभिन्न प्रकार के स्लीपरो की तुलना (1) 03.02 लचीले बंधन (1) 03.03 स्लीपर बिछाना (1) 04. PLANNING OF NON-STOCK ITEMS AND PROCESSING OF REQUISITION (1) 04.01 ट्रैक के लिए बैलास्ट प्रोफाइल (1) 04.02 फार्मेशन (1) 04.03 ब्रिज (पुल) (1) 05 पाइंट्स तथा क्रासिंग - परिचय एवं परिभाषाए (1) 05 PLANNING OF STOCK ITEMS & SYSTEMS OF RECOUPMENT (1) 05.01 विषेश ले आउट (1) 05.02 पृथक्रकरण (आइसोलेशन ) (1) 05.03 तथा क्रासिंग का अनुरक्षण तथा निरक्षण (1) 05.04 पॉइंट्स एवं क्रासिंग की (1) 06 गोलाई का प्ररंभिक ज्ञान (1) 06 PURCHASE POLICY (1) 06.01 वर्को का पुनः संरेखण (1) 07 Purchase Procedure on zonal Railways (1) 08 TENDER EVALUATION AND MISCELLANEOUS POLICY ISSUES IN PURCHASES (1) 08.01 व्यव्स्तिथ ओवरहालिंग (1) 08.02 रेलपथ अनुरक्षण का वार्षिक कार्यक्रम (1) 08.04 गहरी छनाई (1) 08.04.1 रेलपथ का उठाना लोवेरिंग तथा क्रीप (1) 08.05 छोटी वेल्डेड रेल ( एसडब्लूआर ) (1) 08.06 आन ट्रैक मशीन (1) 08.07 छोटी ट्रैक मशीने (1) 08.09 विद्युतीकृत सेक्शन में हाइट गेज (1) 08.11 अंडर ट्रायल सामग्री का रिकॉर्ड (1) 09 गति प्रतिबन्ध और संकेतक (1) 09 Receipt And Inspection of stores (1) 09.01 ठेकेदार की सुरक्षित कार्य प्रणाली (1) 09.03 रेल संरक्षा आयुक्त की स्वीकृति वाले कार्य (1) 10 निरक्षण का उद्देश्य (1) 10 ISSUE AND DISTRIBUTION OF STORES (1) 10.01 राइडिंग गुणवत्ता तथा राइडिंग इंडेक्स (1) 10.03 सिटीआर तथा टीजीआई (1) 10.04 रेलपथ प्रबंधन पध्दति (टीऍमएस ) (1) 11 RETURNED STORES (1) 11.01 स्लीपरो का बिछाना (1) 12 दुर्घटना (1) 12 Scrap Disposal (1) 12.01 ब्रीच (1) 12.02 डाईवर्शन (1) 13 INVENTORY MANAGEMENT (1) 14 लंबी वेल्डित रेल (परिभाषाए) (1) 14.01 एलडब्लूआर / सीडब्लूआरके लिये स्वीकृत स्थान (1) 14.02 एलडब्लूआरकी डीस्ट्रेसिंग (1) 14.03 एलडब्लूआर / सीडब्लूआर का अनुरक्षण (1) 14.04 रेलपथ पर्येवेक्षक - मेट तथा चाबीदार के लिए अनुमत तथा निषिद्ध कार्य (1) 15 - सर्वेक्षण (1) 15 बयाना राशि और जमानत राशि (1) 15.01 SURVEYING (2) 16 रेलवे टेंडर सिस्टम (Railway Tender System) (1) Accidents (2) Active & Passive Earth Pressure (1) Anti corrosive treatment (1) Ballast (2) Bearings in Bridge (1) Blanketing Material (1) Bridges (2) Buckling of track (1) Building Work (1) Cant deficiency & Cant Excess (1) Census (1) Chequered Tiles (1) Chlorination of Water (2) Chlorination Practices (1) Chlorine demand (1) Civil Engineering - Bridges (2) Civil Engineering - P Way (40) Civil Engineering - Works (5) CMS Crossing (1) Completion report (1) Contour & Contour interval (1) Correction Slip (1) CRS Sanction (1) CTR and TGI Value (1) Curing of Concrete (1) curves (2) Deep Screening (2) Design mode (1) Design of concrete mix (2) Destressing (1) Disinfection of water (1) disposal of human waste: (1) Distressed bridges (2) Distressing of LWR (2) distribution System (1) dry density (1) Duties (3) Duties & Responsibilities (9) Duties of Gateman (1) E01.02 Duties of Keyman / Mate / PWS (1) E02.01 Permanent Way (1) E02.02 Handling of 90 UTS rails (1) E02.05 Rail Temperature (1) E02.06 Rail Joints (1) E02.07 Maintenance of Rail Joints (1) E03.01 SLEEPERS AND FASTENINGS - Functions of Sleepers (1) E03.02 Comparison between Various Types of Sleepers (1) E03.04 Laying of Sleepers (1) E04.02 Ballast Profile for L.W.R. track (1) E04.04 Bridges (1) E05.01 Points & Crossings: Introduction & Definitions (1) E05.04 Maintenance and Inspection of Points and Crossing (1) E05.05 Reconditioning of Points and Crossing (1) E06.01 Basics of Curves (1) E06.02 Realignment of Curve (1) E08.01 MAINTENANCE OF TRACK-Through packing (1) E08.02 Systematic Overhauling (1) E08.03 Annual Programme for Regular Track Maintenances (1) E08.04 Lifting/ Lowering of Track and Creep (1) E08.05 Deep Screening (1) E08.06 Short Welded Rail (1) E08.07 Maintenance of SWR (1) E08.10 Level Crossing (1) E08.11 Equipments at Level Crossing (1) E08.12 Maintenance / Examination / Inspection of Level Crossing / Gate (1) E08.14 Welding of Rails (1) E08.15 Records of Material under Trial (As per Cs.no 99) (1) E09.01 Speed Restriction and Indicators (1) E09.02 Safe Working of Contractors (As per Cs.No 95) (1) E09.03 Works Requiring CRS Sanction (1) E10.01 INSPECTION OF TRACK - Object of Inspection (1) E10.02 Riding Quality and Riding Index (1) E10.03 Track Recording and Oscillograph Car (1) E10.04 CTR and TGI Value (1) E12.01 ACCIDENTS AND BREACHES - Accidents (1) E12.02 Breaches (1) E12.03 Diversion (1) E14.01 LONG WELDED RAIL - Definitions (1) E14.02 Permitted locations for LWR/CWR (1) E14.04 Maintenance of LWR / CWR (1) E14.05 DOs and Don’ts OF LWR For PWM / MATES & KEYMAN (1) Egineering (1) Elastic Fastening (1) Elastic Rail Clip (1) Encroachments of Railway land. (2) Engineering (26) Engineering - Book (3) Examination of Rails (2) Fabrication of Glued joint IN SITU. (1) Flushing cisterns (1) FOB (1) Gateman (2) Greasing of ERCs (1) Grow More Food Scheme (1) Guideline (3) H02 भण्डार विभाग का महत्व (1) H03 भण्डार डिपो की संरचना (1) H04 भण्डार का वर्गीकरण (1) H05 कोडिफीकेशन (1) H06 मानकीकरण एवं उसकी उपयोगिता (1) H07 वित्तीय औचित्य के सिध्दांत (1) H08 क्रय के विभिन्न माध्यम (1) H09 क्रय में विविध अधिमान्यताए (1) H10 भण्डार विभाग के अधिकारियो की क्रय शक्तियां (1) H12 निविदा समिति (1) H13 अनुबंध (1) H16 स्थानीय खरीद (1) H17 भण्डार डिपो में भण्डार प्राप्ति के स्त्रोत (1) H18 महत्वपूर्ण वस्तुए एवं उनकी खरीद (1) H19 भण्डार डिपो का संगठन एवं कार्य (1) H20 प्राप्ति अनुभाग की क्रिया - विधि (1) H21 वार्ड की क्रिया - विधि (1) H22 प्रेषण अनुभाग की क्रिया - विधि (1) H23 बहीखाता अनुभाग की क्रिया - विधि (1) H24 डिपो प्रणाली (1) H25 भण्डार का निरीक्षण (1) H26 अस्वीकृत भण्डार (1) H27 लौटाया गया भण्डार (1) H28 अग्रदाय भण्डार (1) H29 अधिशेष भण्डार (1) H30 रेल सामग्री की बिक्री (1) H31 रद्दी माल और नीलामी बिक्रिया (1) H32 वस्तु - सूची नियंत्रण (1) H33 स्टॉक सत्यापन (1) H34 मांगकरताओ व्दारा डिपुओ से भण्डार प्राप्त करने की प्रक्रिया (1) H35 संक्षिप्त टिप्पणीयां (1) Handling of 90 UTS Rails (1) Height Gauges on Electrified Section (1) Honey combing of concrete & its prevention (1) Hot Weather Patrolling (1) Imprest Store (1) INDEX (2) Indicator Boards & Signages (1) Inspection (6) Insulated joints (1) Isolation (1) Keyman / Mate / PWS (3) Laying of Sleepers (1) LDCE Exam (3) Level Crossing (2) Level crossings (2) Licensing Railway Land cultivation (1) Liner Biting (1) LWR (6) Maintenance (2) Maintenance in Electrified Area (2) Maintenance of CMS Xing (1) Maintenance of P Way (5) Maintenance of Rail Joints (1) Maintenancee of SWR (1) Manson precaution (1) Monsoon Patrolling (2) Numerical rating system (NRS) (1) Optimum moisture content (1) P Way (23) Pandrol Clip (1) pass (1) Patrolling of Rail Permanent Way (6) Permanent Way (2) Permanent Way (P Way) (10) Pile Foundation (1) Points and Crossing (3) Protection of Rail (1) Pumping Water Level (1) PWI (1) PWI / AEN / DEN (1) quality control (2) Question & Answer (62) Rail Clusters (1) Rail Formation (2) rail fracture (1) Rail Joints (1) Rail Renewal (3) Rail Welding (3) Rails Defects (2) Railway Affecting Works (1) Railway Construction (1) Railway Organisation (2) Realignments of Curve) (1) Reconditioning of Points and Crossing (1) Rehabilitation of Bridges (1) Renewal of Rail (1) River Training protection work (1) safe speed (1) Safe Working (1) Safety at P. Way Work Site (1) Schedule of Inspection of Bridges (1) Short Note - Bridge (8) Short Note - P Way (48) Short Note - Works (35) Short Notes - Mislanious (7) Sleeper (4) Sleeper Cribs (1) Soil Consistency (1) Special Layouts (2) Speed Restriction and Indicators (2) Static Water Level (1) Steel Structures (1) Stock sheet (1) Store (34) super elevation (1) Tender System (1) Testing of Rails (2) TGI and OMS (1) Thermit Welding (1) Through Parking (2) Tiles (2) Track Circuited Areas (2) Track Inspection (1) Track Machines (6) Track Management System (1) Track Tolerances (2) track-Overhauling (1) Transitions (1) Turnout (1) urinals (1) USFD (2) Venerable location (1) VIDEO (2) wash basin. (1) Washable Aprons (1) Water Cement ratio (1) Water closetsu (1) Water Quality (1) Water Supply (1) Waterproofing (1) weld failure (1) Well Foundation (1) Winter Precautions (1) Workability of Concrete (1) Working of Contractors (2) works (9) कार्य एवं उद्देश्य (1) ट्रैक रिकॉर्डिंग तथा दोलन लेखी कार (1) रेल पथ मेट के कर्तव्य (1)